Free construction rate guide

How much does it cost to build?

Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.

Civil engineering

Granular sub-base, laid & compacted

1 activity  
🏗

Buildings

Blockwork, supply & lay

1 activity  

Stay informed

New rate guides added regularly. Get an email the moment fresh rates go live.

Civil engineering rates

Tap any activity to see the full breakdown

🧱
Granular sub-base
per m³ laid & compacted
£58 – £144 / m³
What is it

A granular sub-base is a dense-graded crushed-rock layer laid onto a prepared formation and compacted in layers to form the load-bearing foundation beneath paving, slabs or a bound surface. In the UK this material is often referred to as Type 1. This rate is the supply, placement and compaction of that granular layer only, measured per m³ of compacted material in place. The material grade is the choice that moves the rate most:

  1. Recycled aggregate — crushed concrete or rubble graded to a Type 1 / dense-graded grading; the cheapest option, subject to grading and acceptance
  2. Virgin aggregate — primary crushed limestone or granite to UK Clause 803; the standard specification

The rate assumes a trimmed, prepared formation is already in place. Excavation to formation, disposal of arisings, any separation membrane and the surfacing above are all separate activities and are excluded.

Rate range by material type
Recycled aggregate (crushed concrete)£58 – £99 / m³
Virgin aggregate (limestone / granite)£93 – £144 / m³

Net rate per m³ placed & compacted, national average, excluding overhead and profit. Within each band the low end is a large machine-laid open area and the high end is small or hand-laid work. Assumes ~2.1 t/m³ compacted with a 5% overfill allowance.

3 key cost drivers
Material type
The delivered aggregate makes up the great majority of the rate, so material grade is the dominant cost. Switching between recycled and virgin aggregate moves the rate more than any other choice.
Placement method & area
Large open areas are machine-laid at high output, spreading plant and mobilisation thinly. Small or restricted areas are hand-laid by a slower gang with a plate compactor and carry part-load and call-out premiums, which lift the per-m³ rate.
Location
London and the South East typically add 15–25% to labour and plant rates.
Estimator

Budget rate generator — choose the material grade and how it is placed

£97 – £126 / m³
Virgin aggregate · medium machine area · national · excl. excavation, membrane, prelims, O&P
Exclusions
  • Excavation to formation level
  • Disposal and haulage of excavated material (arisings)
  • Capping layer beneath the sub-base
  • Formation / subgrade trimming, regulating and proof-rolling
  • Lime or cement stabilisation of the subgrade
  • Geotextile separation or stabilisation membrane
  • Compaction testing — CBR, plate-load or nuclear-density-gauge
  • Sub-base regulating / blinding to surfacing tolerance
  • Edgings, kerbs and channels to contain the layer
  • Prime coat to the finished sub-base
  • Surfacing — bound courses, slabs or block paving above
  • Very small quantities under ~10 m³ — minimum loads and gang call-out push the per-m³ cost above this calculator's range
  • Heavy-duty / high-CBR specifications requiring additional compaction passes or thicker construction
  • Contaminated or unsuitable material assessment and specialist disposal
  • Setting out and survey
  • Night, weekend or phased-working premiums
  • Road-opening permits and licences
  • Traffic management and temporary works
  • Preliminaries, overhead and profit
  • VAT
Related activities
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Buildings rates

Tap any activity to see the full breakdown

Blockwork
per m² supply & lay
£56 – £188 / m²
What is it

Blockwork is the building of walls from precast concrete blocks bedded in mortar. This guide gives a budget rate for supplying and laying one m² of single-skin wall. A key cost driver is the block thickness. Here are the three common blocks and where they’re used:

  1. 100mm lightweight — partition and inner-leaf blocks, cheap and quick to lay
  2. 140mm standard — medium-dense for load-bearing walls
  3. 215mm dense — heavy blocks for solid, load-bearing and party walls
Rate range by block type
100mm lightweight£56 – £101 / m²
140mm standard load-bearing£72 – £129 / m²
215mm dense£109 – £188 / m²

Budget rate per m² of single-skin wall, supply and lay

3 key cost drivers
Block type
Dense, thicker blocks cost more each and lay slower; lightweight, thinner blocks are cheaper and quicker to lay.
Wall complexity
A straight wall with no openings lays fastest. Openings, chases and a fair-faced finish add setting-out, cutting and extra care that slow the gang.
Location
London and South East typically add 15–25% to labour and supervision. Not included in stated figures.
Estimator

Budget rate generator

£83 – £108 / m²
The rate covers blocks, mortar, the laying gang, and overhead & profit.
Exclusions
  • Damp-proof courses (DPC) and cavity trays
  • Lintels and padstones over openings
  • Cavity fill / insulation
  • Movement joints and sealants
  • Painted or rendered finish and separate pointing
  • Scaffold supply (priced in main contractor prelims)
  • Lifting equipment — telehandler / forklift and hoist (priced in main contractor prelims)
  • Very small quantities
  • Preliminaries — main-contractor site set-up, management & welfare
  • VAT
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools