Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.
Tap any activity to see the full breakdown
Excavation is the removal of material from its in-situ position. The three methods of excavation are:
Disposal and haulage of excavated material are separate and subsequent activities.
Labour and plant only in GBP. All methods exclude disposal / haulage, trench support, imported backfill, prelims, overhead & profit.
Budget rate generator
Reinforced concrete (RC) is concrete cast around a steel reinforcement cage to create load-bearing structural elements — foundations, walls, columns, beams and slabs. This all-in rate covers three cost components:
Excavation, blinding concrete, waterproofing and contractor prelims are all priced separately.
All-in rate in GBP. Excludes prelims and O&P. Ranges shown cover low to high rebar density within each element type.
Budget rate generator
Asphalt (tarmac) surfacing is the laying of hot bituminous bound courses onto a prepared sub-base to form a trafficked surface for roads, car parks, driveways and footways. This rate is the supply and laying of the bound courses only; the build-up depends on which courses you lay and how thick:
The rate excludes planing, and assumes a compacted sub-base is already in place.
Net rate per m² of finished surface, national average, excluding overhead and profit. Within each band the low end is a large machine-paved area at minimum depth and the high end is small or hand-laid work at maximum depth.
Budget rate generator
A granular sub-base is a dense-graded crushed-rock layer laid onto a prepared formation and compacted in layers to form the load-bearing foundation beneath paving, slabs or a bound surface. In the UK this material is often referred to as Type 1. This rate is the supply, placement and compaction of that granular layer only, measured per m³ of compacted material in place. The material grade is the choice that moves the rate most:
The rate assumes a trimmed, prepared formation is already in place. Excavation to formation, disposal of arisings, any separation membrane and the surfacing above are all separate activities and are excluded.
Net rate per m³ placed & compacted, national average, excluding overhead and profit. Within each band the low end is a large machine-laid open area and the high end is small or hand-laid work. Assumes ~2.1 t/m³ compacted with a 5% overfill allowance.
Budget rate generator — choose the material grade and how it is placed
Tap any activity to see the full breakdown
Tiling is the supply and fixing of ceramic, porcelain or natural-stone tiles to floors and walls. This is a net rate per m² of finished tiling, blended across floor and wall work, covering tile supply, adhesive, grout, minor substrate patching and the fixing labour. The tile itself is the biggest variable — an £8/m² ceramic and a £300/m² stone are the same trade and unit but a completely different rate.
Removing old tiles, levelling the substrate, tanking to wet areas and underfloor heating are priced separately and are not part of this rate.
Net rate per m² of finished tiling — national average, floor and wall blended, before overhead and profit. Within each tile type, a large simple floor sits at the low end and a small intricate room at the high end. London and the South East add roughly 18% to the labour element.
Blockwork is the building of walls from precast concrete blocks bedded in mortar — the workhorse walling material for commercial and industrial structures. This is the net rate to supply and lay one m² of single-skin wall, and it depends mostly on the block:
The rate covers blocks, mortar and the laying gang only. DPC, lintels, wall ties, cavity insulation and any applied finish are measured separately.
Net rate per m² of wall, supply and lay, national average, excluding prelims and O&P. Within each band the low end is a simple wall at low level and the high end is complex detailing worked above 5 m. London & SE typically adds 15–25% on labour and plant.
Budget rate generator
Brickwork is the building of walls from fired-clay or concrete bricks bedded in mortar — the facing and structural skin of most UK buildings. This is the net rate to supply and lay one m² of brickwork, and it depends mostly on the brick and the bond:
The rate covers bricks, mortar, the laying gang and mixing/loading-out plant only. DPC, lintels, wall ties, cavity insulation, separate pointing and any applied finish are measured separately.
Net rate per m² of wall, supply and lay, national average, excluding prelims and O&P. Within each band the low end is a simple half-brick stretcher wall at low level and the high end is decorative or detailed work above 5 m. Top-end gauged and heritage brickwork can exceed the range. London & SE typically adds 15–25% on labour and plant. Rates are net of overhead & profit — add about 15–25% for a subcontractor all-in rate.
Budget rate generator
Painting and decorating covers the application of paint to interior walls, ceilings, joinery and metalwork. The rate varies enormously depending on the surface preparation required — new plasterboard with a mist coat and two top coats is cheap and fast; old surfaces with multiple layers, staining and damage can require significant prep before painting begins. Premium paints, specialist coatings (fire-retardant, epoxy, anti-mould) and high working heights all add to the rate.
Labour and materials in GBP. Excludes specialist coatings, scaffold, prelims, overhead & profit.
Labour and materials budgeting guide only — not a tender price.
Per tonne supply & fix — often priced separately in a BoQ
Reinforcement is the supply and fixing of steel reinforcement bars (rebar) within concrete elements. In a bill of quantities, rebar is often measured and priced separately from the concrete and formwork. The rate per tonne covers bar supply, delivery, cutting and bending to schedule, and fixing in position including tying wire, spacers and supports. Bar diameter, quantity and fixing complexity are the primary cost drivers.
Supply and fix in GBP. Excludes concrete, formwork, prelims, overhead & profit.
Supply and fix budgeting guide only — not a tender price.
Per m² supply, fix & strike — often priced separately in a BoQ
Formwork is the temporary mould into which concrete is poured. It must be erected before the pour, propped and checked, then struck (removed) after the concrete has cured. The rate covers supply of formwork materials, erection, striking and cleaning for reuse. Formwork is often the most expensive component of a reinforced concrete element — a complex bespoke form can cost more per m² than the concrete itself.
Supply, erect and strike in GBP. Excludes concrete, rebar, prelims, overhead & profit.
Supply, erect and strike budgeting guide only — not a tender price.