Free construction rate guide

How much does it cost to build?

Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.

Civil engineering

Excavation, reinforced concrete, asphalt surfacing and sub-base

4 activities  
🏗

Buildings

Tiling, blockwork, brickwork and painting

4 activities  

Civil engineering rates

Tap any activity to see the full breakdown

Excavation
per m³
£15 – £380 / m³
What is it

Excavation is the removal of material from its in-situ position. The three methods of excavation are:

  1. Machine excavation — the standard approach; fast digging with an excavator
  2. Hand excavation — manual digging with shovels; slower but the safer method when services are present
  3. Vacuum excavation — specialist suction equipment; faster than hand digging but still safe for digging near services

Disposal and haulage of excavated material are separate and subsequent activities.

Rate range by method
Machine excavation£15 – £85 / m³
Hand excavation£83 – £272 / m³
Vacuum excavation£74 – £380 / m³

Labour and plant only in GBP. All methods exclude disposal / haulage, trench support, imported backfill, prelims, overhead & profit.

3 key cost drivers
Method
Machine, hand and vacuum excavation are very different operations. The method alone can shift the rate by 10×.
Ground conditions
Softer ground is faster to dig. When ground gets firm, it can require breaking with a breaker attachment which adds to time and cost.
Location
London and South East typically add 15–25% to labour and plant rates.
Estimator

Budget rate generator

£28 – £45 / m³
Machine · firm ground · labour and plant only · excl. disposal, haulage, prelims, O&P
Exclusions
  • Disposal and haulage of excavated material (priced separately)
  • Trench support and shoring
  • Dewatering and groundwater control
  • Imported backfill or filling material
  • Rock breaking or blasting
  • Service diversions or protection
  • Compaction of fill or formation
  • Contaminated ground assessment and specialist disposal
  • Very small quantities — machine and vacuum excavation carry minimum call-out charges which may dominate the unit rate
  • Preliminaries, overhead and profit
  • VAT
🏗
Reinforced concrete
per m³ all-in
£400 – £2,300 / m³
What is it

Reinforced concrete (RC) is concrete cast around a steel reinforcement cage to create load-bearing structural elements — foundations, walls, columns, beams and slabs. This all-in rate covers three cost components:

  1. Concrete supply and placement — ready-mix concrete delivered, pumped and placed by the pour gang
  2. Reinforcement — rebar supply, cutting, bending and fixing in position
  3. Formwork — shuttering supply, erection and striking

Excavation, blinding concrete, waterproofing and contractor prelims are all priced separately.

Rate range by element type
Ground slab£360 – £820 / m³
Raised flat slab£670 – £1,200 / m³
RC wall£900 – £1,500 / m³
Column or beam£1,240 – £1,930 / m³
Complex bespoke£1,470 – £2,220 / m³

All-in rate in GBP. Excludes prelims and O&P. Ranges shown cover low to high rebar density within each element type.

3 key cost drivers
Element type
The element type is the dominant driver because it determines the formwork surface ratio. A ground slab needs only edge formwork, while a wall needs both faces formed and a column has many faces relative to a small cross-section.
Rebar density
Rebar density is specified independently by the structural engineer and can vary widely within any element type. Reinforcement is priced by the tonne, so density directly affects the composite rate.
Location
London and South East typically add 15–30% to labour and plant rates.
Estimator

Budget rate generator

£783 – £997 / m³
Raised flat slab · typical rebar · all-in · excl. prelims, O&P
Exclusions
  • Excavation to formation level
  • Blinding concrete (priced separately)
  • Waterproofing membranes or tanking
  • Concrete testing and trial mixes
  • Post-tensioning or pre-stressing
  • Concrete finishes beyond standard tamped or floated
  • Small pours under 10 m³ — higher per-m³ cost due to minimum pump charges and crew setup
  • Very heavily reinforced columns or beams (300+ kg/m³) — high fixing complexity pushes rates above this calculator's scope
  • Preliminaries, overhead and profit
  • VAT
Related activities
🛳
Asphalt surfacing
per m² supply & lay
£15 – £120 / m²
What is it

Asphalt surfacing covers the supply and laying of bituminous surfacing to roads, car parks, paths and paved areas. A full construction typically has two layers: a base course (binder or lower layer) and a wearing course (the finished surface). The rate covers material supply and laying only — it assumes the sub-base is already in place. Area size, number of layers and accessibility are the main drivers. Large open areas with paving machines are cheap; small patching in restricted locations is expensive.

Rate range
Cheap
£15 – £28 / m²
Typical
£28 – £65 / m²
High
£65 – £120 / m²

Supply and lay in GBP. Assumes sub-base already prepared. Excludes prelims, overhead & profit.

3 key cost drivers
Number of layers
A base course only is cheapest. A wearing course only is for overlays. Both layers together represent a full new construction — approximately double the single-layer rate.
Area
Large areas (500m²+) allow paving machines to work efficiently with minimal setup cost per m². Small areas require hand laying or small plant — expensive regardless of specification.
Access and constraints
Open road or car park with good access is straightforward. Restricted areas around plant, in tight car parks or near buildings require hand laying, smaller plant and slower progress.
Estimator

Supply and lay budgeting guide only — not a tender price.

£36 – £67 / m²
Supply and lay · assumes sub-base in place · excl. sub-base, kerbing, prelims, O&P
Exclusions
  • Sub-base excavation and construction
  • Kerbing and edging (priced separately)
  • Road markings and studs
  • Traffic management
  • Existing surface removal and disposal
  • Drainage channels and gullies
  • Preliminaries, overhead and profit
  • VAT
🧱
Sub-base (Type 1)
per m³ laid & compacted
Coming soon
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Buildings rates

Tap any activity to see the full breakdown

Tiling — floor
per m² supply & fix
£40 – £500 / m²
What is it

Tiling is the supply and fixing of ceramic, porcelain, or natural stone tiles to floors. The rate covers tile supply, adhesive, grout, and basic surface preparation. The tile itself is the single biggest variable — a £10/m² ceramic and a £300/m² marble are the same trade, same unit, completely different rate.

Rate range
Cheap
£40 – £80 / m²
Typical
£80 – £150 / m²
High
£150 – £500 / m²

All-in rates (tile supply + labour) in GBP. Excludes prelims, overhead & profit.

3 key cost drivers
Tile cost
The tile itself often costs more than the labour. £10/m² ceramic vs £300/m² marble = completely different job.
Cutting required
Small or irregular rooms mean more cuts, more waste, slower productivity. A big open floor is much faster to tile.
Tile size
Mosaics and small tiles take far longer to lay. Large format tiles cover ground quickly but need a flatter substrate.
Estimator
£115 – £165 / m²
All-in rate · tile supply + labour · excl. prelims, O&P
Exclusions
  • Preliminaries (site setup, supervision, welfare)
  • Contractor overhead and profit
  • Removal and disposal of existing tiles
  • Substrate preparation beyond minor patching
  • Waterproofing / tanking membranes
  • Movement joints and specialist trims
  • Underfloor heating supply or installation
  • Wall tiling (separate rate applies)
  • VAT
🧱
Blockwork
per m² supply & lay
£30 – £120 / m²
What is it

Blockwork is the construction of walls using precast concrete blocks bonded with mortar. It is the most common walling material in commercial and industrial construction — fast to lay, structurally capable, and easy to build around openings. Blocks range from 100mm lightweight partition blocks to 215mm dense aggregate blocks for structural or below-ground use. The rate covers blocks, mortar and laying — but not DPC, lintels, cavity fill, ties or any applied finish.

Rate range
Cheap
£30 – £48 / m²
Typical
£48 – £78 / m²
High
£78 – £120 / m²

Supply and lay in GBP. Excludes DPC, lintels, ties, finishes, prelims, overhead & profit.

3 key cost drivers
Block type and weight
100mm lightweight blocks are cheap to supply and quick to lay. 215mm dense aggregate blocks are heavier, slower to handle and more expensive. Dense blocks below ground carry an additional material premium.
Wall complexity
Simple straight walls with few openings are the fastest. Multiple openings, reveals, chases and complex returns reduce productivity significantly — more cuts, more setting out, slower overall output.
Working height
Ground floor walls under 3m are straightforward. Above 3m, scaffold lifts add cost and slow the operation. High gable walls require more scaffold moves and slower working at height.
Estimator

Supply and lay budgeting guide only — not a tender price.

£22 – £38 / m²
Supply and lay · excl. DPC, lintels, ties, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC)
  • Lintels over openings
  • Cavity wall ties and insulation
  • Movement joints and sealants
  • Plastering, rendering or any applied finish
  • Scaffold supply (usually in preliminaries)
  • Preliminaries, overhead and profit
  • VAT
🏠
Brickwork
per m² supply & lay
£55 – £250 / m²
What is it

Brickwork is the construction of walls using fired clay bricks bonded with mortar. Common bricks are used where the face is not visible; facing bricks are specified for external elevations and feature walls. The rate covers brick supply, mortar and laying to a standard bond. Decorative bonds, arches, soldier courses and complex detailing all reduce productivity significantly and should be noted separately when pricing.

Rate range
Cheap
£55 – £95 / m²
Typical
£95 – £165 / m²
High
£165 – £250 / m²

Supply and lay in GBP. Excludes DPC, lintels, scaffold, finishes, prelims, overhead & profit.

3 key cost drivers
Brick type and cost
Common bricks are cheap. Standard machine-made facing bricks are mid-range. Hand-made or specialist facing bricks are expensive — the material cost alone can represent 60% of the total rate.
Bond and complexity
Standard stretcher bond is the fastest. English or Flemish bond uses more bricks and more cuts per m². Feature panels, arches and string courses are significantly more time-consuming to set out and lay.
Quantity
Large areas of repeating brickwork allow continuous gang working. Small isolated panels — parapet cappings, feature insets, repairs — carry a high setup cost per m² regardless of the brick used.
Estimator

Supply and lay budgeting guide only — not a tender price.

£60 – £108 / m²
Supply and lay · excl. DPC, lintels, scaffold, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC)
  • Lintels and arch formers
  • Cavity wall ties and cavity insulation
  • Pointing and repointing (priced separately)
  • Scaffold supply (usually in preliminaries)
  • Rendering or other applied finish
  • Preliminaries, overhead and profit
  • VAT
🖌
Painting & decorating
per m²
£4 – £35 / m²
What is it

Painting and decorating covers the application of paint to interior walls, ceilings, joinery and metalwork. The rate varies enormously depending on the surface preparation required — new plasterboard with a mist coat and two top coats is cheap and fast; old surfaces with multiple layers, staining and damage can require significant prep before painting begins. Premium paints, specialist coatings (fire-retardant, epoxy, anti-mould) and high working heights all add to the rate.

Rate range
Cheap
£4 – £8 / m²
Typical
£8 – £18 / m²
High
£18 – £35 / m²

Labour and materials in GBP. Excludes specialist coatings, scaffold, prelims, overhead & profit.

3 key cost drivers
Surface preparation
New plasterboard needs a mist coat and minimal prep. Old surfaces may need washing, sugar soaping, sanding, filling and priming before painting can begin. On large areas, prep can take as long as the painting itself.
Paint quality and coats
Trade emulsion at 2 coats is the baseline. Premium paints with 3 coats, specialist anti-mould, fire-retardant or epoxy coatings all carry higher material costs. Specialist coatings can be 5–10× the cost of standard emulsion.
Working height
Standard ceiling height (under 3m) is straightforward. Above 3m, painters need hop-ups or scaffold towers. High ceilings, atria and stairwells add significant cost — slower working, more equipment, higher risk.
Estimator

Labour and materials budgeting guide only — not a tender price.

£3 – £6 / m²
Labour and materials · excl. specialist coatings, scaffold, prelims, O&P
Exclusions
  • Wallpaper, fabric or specialist wall coverings
  • Joinery and metalwork painting (priced by item or run)
  • External painting (different system, separate rate)
  • Scaffold supply and erection
  • Removal and disposal of old coatings (e.g. lead paint)
  • Rendering or plastering preparation
  • Preliminaries, overhead and profit
  • VAT
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Reinforcement (rebar)

Reinforced concrete component

Per tonne supply & fix — often priced separately in a BoQ

Reinforcement (rebar)
per tonne supply & fix
£900 – £2,500 / t
What is it

Reinforcement is the supply and fixing of steel reinforcement bars (rebar) within concrete elements. In a bill of quantities, rebar is often measured and priced separately from the concrete and formwork. The rate per tonne covers bar supply, delivery, cutting and bending to schedule, and fixing in position including tying wire, spacers and supports. Bar diameter, quantity and fixing complexity are the primary cost drivers.

Rate range
Cheap
£900 – £1,200 / t
Typical
£1,200 – £1,800 / t
High
£1,800 – £2,500 / t

Supply and fix in GBP. Excludes concrete, formwork, prelims, overhead & profit.

3 key cost drivers
Bar size and type
Large straight bars (T25, T32) are fast to fix per tonne. Small bars (T10, T12) require more cuts, more ties and more handling time — the same weight takes much longer to place.
Fixing complexity
Simple mats or straight bars in an open slab fix quickly. Congested column cages with complex shapes, laps and links are slow and require skilled fixers throughout.
Quantity
Large tonnages reduce the amortised cost of mobilisation, delivery and setup. Small quantities on a minor job carry a premium — there is no economy of scale.
Estimator

Supply and fix budgeting guide only — not a tender price.

£1,150 – £1,750 / t
Supply and fix · excl. concrete, formwork, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Formwork supply and striking
  • Reinforcement mesh (A-type — priced separately)
  • Post-tensioning cables or tendons
  • Stainless steel or specialist alloy bars
  • Preliminaries, overhead and profit
  • VAT

Formwork

Reinforced concrete component

Per m² supply, fix & strike — often priced separately in a BoQ

📐
Formwork
per m² supply, fix & strike
£25 – £200 / m²
What is it

Formwork is the temporary mould into which concrete is poured. It must be erected before the pour, propped and checked, then struck (removed) after the concrete has cured. The rate covers supply of formwork materials, erection, striking and cleaning for reuse. Formwork is often the most expensive component of a reinforced concrete element — a complex bespoke form can cost more per m² than the concrete itself.

Rate range
Cheap
£25 – £55 / m²
Typical
£55 – £110 / m²
High
£110 – £200 / m²

Supply, erect and strike in GBP. Excludes concrete, rebar, prelims, overhead & profit.

3 key cost drivers
Element type
Flat slab formwork on a repetitive floor plate is the most efficient. Walls need two-sided forms. Complex shaped elements need bespoke carpentry — the most expensive category.
Repetition and reuse
Proprietary systems designed for multiple reuses amortise cost over many cycles. Bespoke one-off timber forms bear their full fabrication cost in a single use — dramatically higher per m².
Area and complexity
Large repetitive areas allow efficient gang working and minimal cuts. Small areas with multiple openings and projections require far more labour per m² regardless of the system.
Estimator

Supply, erect and strike budgeting guide only — not a tender price.

£65 – £115 / m²
Supply, erect and strike · excl. concrete, rebar, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Reinforcement supply and fixing
  • Temporary propping beyond standard (priced separately)
  • Permanent lost formwork (e.g. Cordeck)
  • Specialist surface finishes to formed faces
  • Preliminaries, overhead and profit
  • VAT