Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.
Granular sub-base, laid & compacted
Blockwork, supply & lay
New rate guides added regularly. Get an email the moment fresh rates go live.
Get updates →Tap any activity to see the full breakdown
A granular sub-base is a dense-graded crushed-rock layer laid onto a prepared formation and compacted in layers to form the load-bearing foundation beneath paving, slabs or a bound surface. In the UK this material is often referred to as Type 1. This rate is the supply, placement and compaction of that granular layer only, measured per m³ of compacted material in place. The material grade is the choice that moves the rate most:
The rate assumes a trimmed, prepared formation is already in place. Excavation to formation, disposal of arisings, any separation membrane and the surfacing above are all separate activities and are excluded.
Net rate per m³ placed & compacted, national average, excluding overhead and profit. Within each band the low end is a large machine-laid open area and the high end is small or hand-laid work. Assumes ~2.1 t/m³ compacted with a 5% overfill allowance.
Budget rate generator — choose the material grade and how it is placed
Tap any activity to see the full breakdown
Blockwork is the building of walls from precast concrete blocks bedded in mortar — the workhorse walling material for commercial and industrial structures. This is the main-contractor budget rate to supply and lay one m² of single-skin wall — the trade’s cost plus subcontractor and main-contractor overhead & profit. It depends mostly on the block:
The rate covers blocks, mortar, the laying gang, site supervision and overhead & profit. DPC, lintels, wall ties, cavity insulation, any applied finish, scaffold, lifting equipment (provided by the main contractor) and preliminaries are measured separately.
Main-contractor budget rate per m² of wall, supply and lay, national average, including subcontractor and main-contractor overhead & profit but excluding preliminaries, lifting equipment (main contractor), scaffold and VAT. Within each band the low end is a simple wall and the high end is complex detailing. London & SE typically adds 15–25% on labour and supervision.
Budget rate generator