Free construction rate guide

How much does it cost to build?

Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.

Civil engineering

Excavation, reinforced concrete, asphalt surfacing and sub-base

4 activities  
🏗

Buildings

Tiling, blockwork, brickwork and painting

4 activities  

Civil engineering rates

Tap any activity to see the full breakdown

Excavation
per m³
£15 – £380 / m³
What is it

Excavation is the removal of material from its in-situ position. The three methods of excavation are:

  1. Machine excavation — the standard approach; fast digging with an excavator
  2. Hand excavation — manual digging with shovels; slower but the safer method when services are present
  3. Vacuum excavation — specialist suction equipment; faster than hand digging but still safe for digging near services

Disposal and haulage of excavated material are separate and subsequent activities.

Rate range by method
Machine excavation£15 – £85 / m³
Hand excavation£83 – £272 / m³
Vacuum excavation£74 – £380 / m³

Labour and plant only in GBP. All methods exclude disposal / haulage, trench support, imported backfill, prelims, overhead & profit.

3 key cost drivers
Method
Machine, hand and vacuum excavation are very different operations. The method alone can shift the rate by 10×.
Ground conditions
Softer ground is faster to dig. When ground gets firm, it can require breaking with a breaker attachment which adds to time and cost.
Location
London and South East typically add 15–25% to labour and plant rates.
Estimator

Budget rate generator

£28 – £45 / m³
Machine · firm ground · labour and plant only · excl. disposal, haulage, prelims, O&P
Exclusions
  • Disposal and haulage of excavated material (priced separately)
  • Trench support and shoring
  • Dewatering and groundwater control
  • Imported backfill or filling material
  • Rock breaking or blasting
  • Service diversions or protection
  • Compaction of fill or formation
  • Contaminated ground assessment and specialist disposal
  • Very small quantities — machine and vacuum excavation carry minimum call-out charges which may dominate the unit rate
  • Preliminaries, overhead and profit
  • VAT
🏗
Reinforced concrete
per m³ all-in
£400 – £2,300 / m³
What is it

Reinforced concrete (RC) is concrete cast around a steel reinforcement cage to create load-bearing structural elements — foundations, walls, columns, beams and slabs. This all-in rate covers three cost components:

  1. Concrete supply and placement — ready-mix concrete delivered, pumped and placed by the pour gang
  2. Reinforcement — rebar supply, cutting, bending and fixing in position
  3. Formwork — shuttering supply, erection and striking

Excavation, blinding concrete, waterproofing and contractor prelims are all priced separately.

Rate range by element type
Ground slab£360 – £820 / m³
Raised flat slab£670 – £1,200 / m³
RC wall£900 – £1,500 / m³
Column or beam£1,240 – £1,930 / m³
Complex bespoke£1,470 – £2,220 / m³

All-in rate in GBP. Excludes prelims and O&P. Ranges shown cover low to high rebar density within each element type.

3 key cost drivers
Element type
The element type is the dominant driver because it determines the formwork surface ratio. A ground slab needs only edge formwork, while a wall needs both faces formed and a column has many faces relative to a small cross-section.
Rebar density
Rebar density is specified independently by the structural engineer and can vary widely within any element type. Reinforcement is priced by the tonne, so density directly affects the composite rate.
Location
London and South East typically add 15–30% to labour and plant rates.
Estimator

Budget rate generator

£783 – £997 / m³
Raised flat slab · typical rebar · all-in · excl. prelims, O&P
Exclusions
  • Excavation to formation level
  • Blinding concrete (priced separately)
  • Waterproofing membranes or tanking
  • Concrete testing and trial mixes
  • Post-tensioning or pre-stressing
  • Concrete finishes beyond standard tamped or floated
  • Small pours under 10 m³ — higher per-m³ cost due to minimum pump charges and crew setup
  • Very heavily reinforced columns or beams (300+ kg/m³) — high fixing complexity pushes rates above this calculator's scope
  • Preliminaries, overhead and profit
  • VAT
Related activities
🛳
Asphalt surfacing
per m² supply & lay
£9 – £123 / m²
What is it

Asphalt (tarmac) surfacing is the laying of hot bituminous bound courses onto a prepared sub-base to form a trafficked surface for roads, car parks, driveways and footways. This rate is the supply and laying of the bound courses only; the build-up depends on which courses you lay and how thick:

  1. Surface course — the wearing course, typically 30–50 mm
  2. Binder course — the intermediate course, typically 50–80 mm
  3. Base course — the structural course, 70–250 mm, laid in two lifts when 150 mm or thicker

The rate excludes planing, and assumes a compacted sub-base is already in place.

Rate range by construction type
Surface course only£9 – £30 / m²
Binder + surface course£21 – £58 / m²
Full construction (base + binder + surface)£37 – £123 / m²

Net rate per m² of finished surface, national average, excluding overhead and profit. Within each band the low end is a large machine-paved area at minimum depth and the high end is small or hand-laid work at maximum depth.

3 key cost drivers
Courses & depth
The number of courses and how thick each one is determines most of the rate. Base depth is the single biggest factor as its depth can vary significantly and sometimes requires two courses.
Area & lay method
Large open areas are machine-paved at high output, spreading plant and mobilisation thinly. Small or restricted areas are hand-laid by a slower gang and carry part-load and call-out premiums, which lift the per-m² rate.
Location & access
London and the South-East typically add 15–25% to the laying labour and plant element. Restricted access, tight urban sites and small quantities also lift the rate significantly — sometimes more than geography alone.
Estimator

Budget rate generator

£29 – £38 / m²
Surface 40mm + binder 60mm · medium machine area · national · excl. prelims, O&P
Exclusions
  • Excavation and disposal to formation level
  • Sub-base or capping supply and lay — the rate assumes a prepared, compacted sub-base
  • Formation or sub-base regulating and trimming to level
  • Prime coat to unbound granular bases
  • Kerbs, edgings and channels
  • Gully gratings and ironwork adjustment to finished level
  • Road markings, studs and signage
  • Traffic management and temporary works
  • Surfacing to very small areas under ~100 m² — minimum asphalt loads and gang call-out push the per-m² cost above this calculator's range
  • High-spec surfaces (SMA, HRA, coloured or porous asphalt) beyond the noted uplift
  • Contaminated planings or coal-tar-bound material — requires specialist assessment and disposal
  • Saw cutting at joints or around ironwork — priced separately per linear metre
  • Night, weekend or phased working premiums
  • Preliminaries, overhead and profit
  • VAT
Related activities
🧱
Granular sub-base
per m³ laid & compacted
£58 – £144 / m³
What is it

A granular sub-base is a dense-graded crushed-rock layer laid onto a prepared formation and compacted in layers to form the load-bearing foundation beneath paving, slabs or a bound surface. In the UK this material is often referred to as Type 1. This rate is the supply, placement and compaction of that granular layer only, measured per m³ of compacted material in place. The material grade is the choice that moves the rate most:

  1. Recycled aggregate — crushed concrete or rubble graded to a Type 1 / dense-graded grading; the cheapest option, subject to grading and acceptance
  2. Virgin aggregate — primary crushed limestone or granite to UK Clause 803; the standard specification

The rate assumes a trimmed, prepared formation is already in place. Excavation to formation, disposal of arisings, any separation membrane and the surfacing above are all separate activities and are excluded.

Rate range by material type
Recycled aggregate (crushed concrete)£58 – £99 / m³
Virgin aggregate (limestone / granite)£93 – £144 / m³

Net rate per m³ placed & compacted, national average, excluding overhead and profit. Within each band the low end is a large machine-laid open area and the high end is small or hand-laid work. Assumes ~2.1 t/m³ compacted with a 5% overfill allowance.

3 key cost drivers
Material type
The delivered aggregate makes up the great majority of the rate, so material grade is the dominant cost. Switching between recycled and virgin aggregate moves the rate more than any other choice.
Placement method & area
Large open areas are machine-laid at high output, spreading plant and mobilisation thinly. Small or restricted areas are hand-laid by a slower gang with a plate compactor and carry part-load and call-out premiums, which lift the per-m³ rate.
Location
London and the South East typically add 15–25% to labour and plant rates.
Estimator

Budget rate generator — choose the material grade and how it is placed

£97 – £126 / m³
Virgin aggregate · medium machine area · national · excl. excavation, membrane, prelims, O&P
Exclusions
  • Excavation to formation level
  • Disposal and haulage of excavated material (arisings)
  • Capping layer beneath the sub-base
  • Formation / subgrade trimming, regulating and proof-rolling
  • Lime or cement stabilisation of the subgrade
  • Geotextile separation or stabilisation membrane
  • Compaction testing — CBR, plate-load or nuclear-density-gauge
  • Sub-base regulating / blinding to surfacing tolerance
  • Edgings, kerbs and channels to contain the layer
  • Prime coat to the finished sub-base
  • Surfacing — bound courses, slabs or block paving above
  • Very small quantities under ~10 m³ — minimum loads and gang call-out push the per-m³ cost above this calculator's range
  • Heavy-duty / high-CBR specifications requiring additional compaction passes or thicker construction
  • Contaminated or unsuitable material assessment and specialist disposal
  • Setting out and survey
  • Night, weekend or phased-working premiums
  • Road-opening permits and licences
  • Traffic management and temporary works
  • Preliminaries, overhead and profit
  • VAT
Related activities
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Buildings rates

Tap any activity to see the full breakdown

Tiling
per m² supply & fix
£40 – £450 / m²
What is it

Tiling is the supply and fixing of ceramic, porcelain or natural-stone tiles to floors and walls. This is a net rate per m² of finished tiling, blended across floor and wall work, covering tile supply, adhesive, grout, minor substrate patching and the fixing labour. The tile itself is the biggest variable — an £8/m² ceramic and a £300/m² stone are the same trade and unit but a completely different rate.

  1. Ceramic — the budget option, lighter and quick to cut and fix
  2. Porcelain — the mid-range workhorse, denser and harder-wearing
  3. Natural stone — premium stone such as marble, granite or limestone, heavier and slower to lay

Removing old tiles, levelling the substrate, tanking to wet areas and underfloor heating are priced separately and are not part of this rate.

Rate range by tile type
Cheap tiles — budget ceramic£40 – £80 / m²
Mid-range tiles — porcelain£80 – £150 / m²
Luxury tiles — marble & stone£150 – £450 / m²

Net rate per m² of finished tiling — national average, floor and wall blended, before overhead and profit. Within each tile type, a large simple floor sits at the low end and a small intricate room at the high end. London and the South East add roughly 18% to the labour element.

3 key cost drivers
Tile cost & spec
The tile is usually the largest single cost and often beats the labour. Budget ceramic to premium stone spans more than 30× on the material alone.
Tile size & layout
Large-format tiles cover ground quickly, while mosaics, small tiles and intricate cutting are slower and waste more. A large, simple, open area is the cheapest to tile and a small or irregular room the most expensive.
Location
London and the South East typically add around 15–20% to labour rates. Tile prices themselves are broadly national.
Estimator
£40
£77 – £100 / m²
Medium tile · standard room · floor & wall blend · national · excl. prelims, O&P
Including a typical contractor margin, the installed price is around £92 – £120 / m².
Exclusions
  • Removal and disposal of existing tiles or floor coverings
  • Substrate preparation beyond minor patching — latex levelling screeds, overboarding, plaster repairs
  • Waterproofing / tanking membranes to wet areas
  • Decorative patterns such as herringbone, diagonal or modular beyond straight lay
  • Epoxy grout, rapid-set and specialist adhesives
  • Movement joints, matwells and specialist trims or profiles
  • Underfloor heating supply or installation
  • Sealing and ongoing aftercare of natural stone
  • Scaffolding or access equipment above ~3 m for high wall tiling
  • Preliminaries, overhead and profit
  • VAT
Related activities
🧱
Blockwork
per m² supply & lay
£35 – £145 / m²
What is it

Blockwork is the building of walls from precast concrete blocks bedded in mortar — the workhorse walling material for commercial and industrial structures. This is the net rate to supply and lay one m² of single-skin wall, and it depends mostly on the block:

  1. 100mm lightweight — partition and inner-leaf blocks, cheap and quick to lay
  2. 140mm standard — medium-dense load-bearing aggregate blocks
  3. 215mm dense — heavy blocks for solid, load-bearing and party walls

The rate covers blocks, mortar and the laying gang only. DPC, lintels, wall ties, cavity insulation and any applied finish are measured separately.

Rate range by block type
100mm lightweight£35 – £78 / m²
140mm standard load-bearing£45 – £100 / m²
215mm dense£69 – £143 / m²

Net rate per m² of wall, supply and lay, national average, excluding prelims and O&P. Within each band the low end is a simple wall at low level and the high end is complex detailing worked above 5 m. London & SE typically adds 15–25% on labour and plant.

3 key cost drivers
Block type & weight
Block type is the single biggest lever on the rate. Lightweight blocks are cheap and quick to lay; dense blocks cost more each, lay slower and use more mortar.
Wall complexity
Straight walls with few openings lay fastest. Openings, returns, chases and reveals add setting-out and cutting that slow the gang.
Location
London and South East typically add 15–25% to labour and plant rates.
Estimator

Budget rate generator

£52 – £67 / m²
140 mm · standard · under 3m · supply and lay · excl. DPC, lintels, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC) and cavity trays
  • Lintels and padstones over openings
  • Cavity wall ties and partial-fill insulation
  • Cavity fill / full-fill insulation
  • Movement joints and sealants
  • Bed-joint reinforcement beyond the sundry allowance
  • Fair-faced or painted finish and separate pointing
  • Plastering, rendering or dry-lining
  • Scaffold supply (usually in preliminaries)
  • Very small quantities — minimum delivery loads and mobilisation can dominate the rate
  • Preliminaries, overhead and profit
  • VAT
🏠
Brickwork
per m² supply & lay
£55 – £250 / m²
What is it

Brickwork is the construction of walls using fired clay bricks bonded with mortar. Common bricks are used where the face is not visible; facing bricks are specified for external elevations and feature walls. The rate covers brick supply, mortar and laying to a standard bond. Decorative bonds, arches, soldier courses and complex detailing all reduce productivity significantly and should be noted separately when pricing.

Rate range
Cheap
£55 – £95 / m²
Typical
£95 – £165 / m²
High
£165 – £250 / m²

Supply and lay in GBP. Excludes DPC, lintels, scaffold, finishes, prelims, overhead & profit.

3 key cost drivers
Brick type and cost
Common bricks are cheap. Standard machine-made facing bricks are mid-range. Hand-made or specialist facing bricks are expensive — the material cost alone can represent 60% of the total rate.
Bond and complexity
Standard stretcher bond is the fastest. English or Flemish bond uses more bricks and more cuts per m². Feature panels, arches and string courses are significantly more time-consuming to set out and lay.
Quantity
Large areas of repeating brickwork allow continuous gang working. Small isolated panels — parapet cappings, feature insets, repairs — carry a high setup cost per m² regardless of the brick used.
Estimator

Supply and lay budgeting guide only — not a tender price.

£60 – £108 / m²
Supply and lay · excl. DPC, lintels, scaffold, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC)
  • Lintels and arch formers
  • Cavity wall ties and cavity insulation
  • Pointing and repointing (priced separately)
  • Scaffold supply (usually in preliminaries)
  • Rendering or other applied finish
  • Preliminaries, overhead and profit
  • VAT
🖌
Painting & decorating
per m²
£4 – £35 / m²
What is it

Painting and decorating covers the application of paint to interior walls, ceilings, joinery and metalwork. The rate varies enormously depending on the surface preparation required — new plasterboard with a mist coat and two top coats is cheap and fast; old surfaces with multiple layers, staining and damage can require significant prep before painting begins. Premium paints, specialist coatings (fire-retardant, epoxy, anti-mould) and high working heights all add to the rate.

Rate range
Cheap
£4 – £8 / m²
Typical
£8 – £18 / m²
High
£18 – £35 / m²

Labour and materials in GBP. Excludes specialist coatings, scaffold, prelims, overhead & profit.

3 key cost drivers
Surface preparation
New plasterboard needs a mist coat and minimal prep. Old surfaces may need washing, sugar soaping, sanding, filling and priming before painting can begin. On large areas, prep can take as long as the painting itself.
Paint quality and coats
Trade emulsion at 2 coats is the baseline. Premium paints with 3 coats, specialist anti-mould, fire-retardant or epoxy coatings all carry higher material costs. Specialist coatings can be 5–10× the cost of standard emulsion.
Working height
Standard ceiling height (under 3m) is straightforward. Above 3m, painters need hop-ups or scaffold towers. High ceilings, atria and stairwells add significant cost — slower working, more equipment, higher risk.
Estimator

Labour and materials budgeting guide only — not a tender price.

£3 – £6 / m²
Labour and materials · excl. specialist coatings, scaffold, prelims, O&P
Exclusions
  • Wallpaper, fabric or specialist wall coverings
  • Joinery and metalwork painting (priced by item or run)
  • External painting (different system, separate rate)
  • Scaffold supply and erection
  • Removal and disposal of old coatings (e.g. lead paint)
  • Rendering or plastering preparation
  • Preliminaries, overhead and profit
  • VAT
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Reinforcement (rebar)

Reinforced concrete component

Per tonne supply & fix — often priced separately in a BoQ

Reinforcement (rebar)
per tonne supply & fix
£900 – £2,500 / t
What is it

Reinforcement is the supply and fixing of steel reinforcement bars (rebar) within concrete elements. In a bill of quantities, rebar is often measured and priced separately from the concrete and formwork. The rate per tonne covers bar supply, delivery, cutting and bending to schedule, and fixing in position including tying wire, spacers and supports. Bar diameter, quantity and fixing complexity are the primary cost drivers.

Rate range
Cheap
£900 – £1,200 / t
Typical
£1,200 – £1,800 / t
High
£1,800 – £2,500 / t

Supply and fix in GBP. Excludes concrete, formwork, prelims, overhead & profit.

3 key cost drivers
Bar size and type
Large straight bars (T25, T32) are fast to fix per tonne. Small bars (T10, T12) require more cuts, more ties and more handling time — the same weight takes much longer to place.
Fixing complexity
Simple mats or straight bars in an open slab fix quickly. Congested column cages with complex shapes, laps and links are slow and require skilled fixers throughout.
Quantity
Large tonnages reduce the amortised cost of mobilisation, delivery and setup. Small quantities on a minor job carry a premium — there is no economy of scale.
Estimator

Supply and fix budgeting guide only — not a tender price.

£1,150 – £1,750 / t
Supply and fix · excl. concrete, formwork, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Formwork supply and striking
  • Reinforcement mesh (A-type — priced separately)
  • Post-tensioning cables or tendons
  • Stainless steel or specialist alloy bars
  • Preliminaries, overhead and profit
  • VAT

Formwork

Reinforced concrete component

Per m² supply, fix & strike — often priced separately in a BoQ

📐
Formwork
per m² supply, fix & strike
£25 – £200 / m²
What is it

Formwork is the temporary mould into which concrete is poured. It must be erected before the pour, propped and checked, then struck (removed) after the concrete has cured. The rate covers supply of formwork materials, erection, striking and cleaning for reuse. Formwork is often the most expensive component of a reinforced concrete element — a complex bespoke form can cost more per m² than the concrete itself.

Rate range
Cheap
£25 – £55 / m²
Typical
£55 – £110 / m²
High
£110 – £200 / m²

Supply, erect and strike in GBP. Excludes concrete, rebar, prelims, overhead & profit.

3 key cost drivers
Element type
Flat slab formwork on a repetitive floor plate is the most efficient. Walls need two-sided forms. Complex shaped elements need bespoke carpentry — the most expensive category.
Repetition and reuse
Proprietary systems designed for multiple reuses amortise cost over many cycles. Bespoke one-off timber forms bear their full fabrication cost in a single use — dramatically higher per m².
Area and complexity
Large repetitive areas allow efficient gang working and minimal cuts. Small areas with multiple openings and projections require far more labour per m² regardless of the system.
Estimator

Supply, erect and strike budgeting guide only — not a tender price.

£65 – £115 / m²
Supply, erect and strike · excl. concrete, rebar, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Reinforcement supply and fixing
  • Temporary propping beyond standard (priced separately)
  • Permanent lost formwork (e.g. Cordeck)
  • Specialist surface finishes to formed faces
  • Preliminaries, overhead and profit
  • VAT