Disposal - Muck-away – cost per m³ – UK 2026 Rate Guide

Budget rate for supply & lay · typical budget rate before your adjustments

The instant AI answer for any UK construction rate — with the full researched Excel build-up behind it
Ask any rate and get an expert, itemised answer in seconds, then request the fully-researched editable Excel.
Disposal - Muck-away
per m³ · supply & lay
£31 – £330 / m³
What is it

Muck-away is the loading, haulage and lawful disposal or recovery of excavated spoil from site.

Rate guide
Standard clean inert soil, normal access and local facility£35 – £53/m³
Segregated clean hardcore or concrete suitable for recovery£31 – £46/m³
Mixed non-hazardous construction spoil£61 – £94/m³
Contaminated non-hazardous soil£83 – £154/m³
Hazardous or specialist-classified material£154 – £330/m³
Labour output
Open site, excavator loading and continuous wagon rotation120–200 m³/day
Normal urban site with moderate wagon turnaround70–120 m³/day
Restricted access, smaller vehicles or intermittent loading30–60 m³/day
Broken-up working, hand assistance or severe traffic constraints10–30 m³/day
Key rate adjusters
Haul distance
Each additional 10 miles of round-trip travel can add about £5–£10/m³ through reduced wagon cycles and higher transport cost.
Waste classification
Reclassification from clean inert to mixed or contaminated material can increase disposal charges by £25–£100/m³ or more.
Bulking and density
Excavation typically increases material volume by 15–30%, raising the actual number of loads unless quantities are assessed on a consistent basis.
Access constraints
Small tippers, difficult reversing or limited loading space can add £12–£30/m³ compared with efficient eight-wheel wagon operations.
Part loads and waiting
Minimum-load charges and wagon standing time can add £150–£300 per visit, often equating to £15–£40/m³ on small quantities.
Testing and compliance
Soil analysis, classification and acceptance testing commonly add £400–£1,200 per waste stream before any abnormal sampling requirements.
Quantity surveyor insights
  • Waste and buildability: Maximise cut-and-fill balance and segregate clean soil, hardcore and suspect material at source; mixing a small contaminated fraction into otherwise clean spoil can increase the disposal rate across the whole stockpile.
  • Scope and procurement: Confirm responsibility for excavation, loading, stockpiling, haul roads, wheel cleaning, testing, waiting time and facility rejection, then obtain quotations tied to named receiving facilities and stated haul distances.

Estimate Anything AI answer · indicative budget rates · updated 31 August 2026