Fabric specification
Increasing tensile strength, puncture resistance or unit weight can add £1.00–£5.00/m² to the installed rate.
Lap allowance
Standard laps typically add 5–12% to fabric consumption, rising to 15–25% on irregular or heavily penetrated layouts.
Order quantity
Small call-offs and fragmented releases can increase rates by 15–40% compared with continuous bulk installation.
Site access
Restricted delivery, double handling or hand carriage can add £1.00–£3.00/m².
Substrate condition
Trimming, stone picking, dewatering or local soft-spot treatment can add £2.00–£8.00/m² where not separately allowed.
Temporary restraint
Pins, staples, sandbags or additional anchoring in exposed conditions can add £0.50–£2.00/m².