Section weight
Light members with a high piece count can increase the tonne rate by 15–30% because fabrication and erection effort is driven more by member numbers than weight.
Connection complexity
Moment connections, stiffeners and extensive plated details typically add £400–£1,200 per tonne compared with standard bolted shear connections.
Protective coating
A basic shop primer may be included, while enhanced paint systems or galvanizing commonly add £250–£700 per tonne.
Access and cranage
Restricted lifting positions, mobile-crane oversailing constraints or tower-crane dependency can increase erection costs by 10–25%.
Programme intensity
Accelerated fabrication, phased deliveries, weekend working or multiple erection gangs can add 8–20% to the steelwork package.
Market quantity
Small or fragmented packages below roughly 50 tonnes can attract premiums of £500–£1,500 per tonne against efficient larger-volume procurement.