C6/8 concrete
per m³ · supply & lay
£137 – £231 / m³
What is it

The supply and placing of GEN0 (C6/8) ready-mixed concrete as mass or trench fill — the low-strength grade used for blinding, backfill and mass foundations — discharged into the works and hand-placed, tamped and compacted, priced per m³ of concrete placed. This headline is a full-pour, direct-discharge rate: the standard case a groundworks bill prices, with pumping, part loads and barrowed delivery as the variants below.

A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 73% of it. On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). Even so the figure lands above the £90–£130/m³ a groundworker quotes for supply-and-lay (myjobquote / RMS / ConcreteMath 2026), which is the expected relationship: a main-contractor budget rate sits at or above a domestic supply-and-lay band, and the concrete still carries the main-contractor margin. That is deliberate, not an error — it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:

  1. Low — larger loads and competitive ready-mix supply.
  2. Standard — a typical project and merchant price; the default rate.
  3. High — smaller loads or higher-cost areas.
Rate range
Low£137 – £177 / m³
Standard£156 – £201 / m³
High£179 – £231 / m³

Budget rate per m³.

3 key cost drivers
Concrete mix & bought-in share
GEN0 (C6/8) ready-mixed concrete is around 73% of the rate, so the mix grade and the delivered merchant price set most of it. A richer grade or a long delivery lifts the material cost — and, because it still carries the main-contractor O&P, the rate per m³ with it.
Pour size & delivery
The headline is a full load discharged straight off the truck. Small or part loads add a surcharge and standing time; pumping adds a line pump and a pump-grade supplement; barrowing or dumpering adds a third operative — the calculator prices the standard direct-discharge case, with these as options.
Supply & quantity
Merchant prices for the bought-in materials move with supplier, account and load size, and the published band already spans that range. Rates are UK non-London; London & the South East typically run dearer — adjust the build-up.
Estimator

Budget rate generator

£156 – £201 / m³
Covers GEN0 (C6/8) ready-mixed concrete, the placing gang & O&P, full pour direct-discharge · excl. formwork, reinforcement, trench excavation, prelims & VAT
Exclusions
  • Formwork, edge shuttering & expansion / movement joints
  • Reinforcement — mesh, bar, chairs & spacers (a separately measured item)
  • Trench or basement excavation, disposal & formation preparation
  • Power-float, brushed / tamped decorative finishes & surface treatments beyond a plain tamped mass-fill finish
  • Pumping, part-load & standing-time surcharges where the pour is not a full direct-discharge load
  • VAT