HB2 Half-Battered Kerb: Supply & Lay – cost per m – UK 2026 Rate Guide

Budget rate for supply & lay · typical budget rate before your adjustments

See the full build-up — try free →
Labour, plant, materials, outputs and waste — yours to edit, as an Excel. Three free.

Rates are UK national (non-London): central London and constrained urban sites typically run dearer — adjust the labour, plant and access lines in the build-up accordingly.

HB2 kerb (half-battered)
per m · supply & lay
£32 – £71 / m
What is it

The supply and laying of a BS EN 1340 HB2 half-battered precast-concrete kerb (125×255×914 mm), set out to line and level on a ~100 mm concrete bed and backed with a concrete haunch to about two-thirds of the kerb height, priced per linear metre of finished straight kerb run. This is the standard external-works kerbing line on UK bills of quantities. The composite carries two operations:

  1. Bed & set out — a ~100 mm GEN1 (C8/10) concrete bed laid to line and level.
  2. Lay & haunch — the HB2 kerb units laid and close-jointed on the bed, backed with a concrete haunch to ~2/3 height and pointed.
Rate range
Low£32 – £41 / m
Typical£39 – £51 / m
High£55 – £71 / m

Budget rate per m³.

3 key cost drivers
Alignment & radius
This rate is a straight run. Gentle and tight radii, quadrants and drop-kerb fittings lay slower (about 4.5–5.5 m/hr on curves versus a straight run), lifting the rate per metre.
Access & bedding / haunch spec
Good access on a residential / light-commercial GEN1 bed is the default. Poor access, long barrow runs, live traffic, or an adoptable-highway C20P bed and deeper haunch add concrete and slow the gang.
Supply & quantity
Merchant prices for the bought-in materials move with supplier, account and load size, and the published band already spans that range. Rates are UK non-London; London & the South East typically run dearer — adjust the build-up.
Estimator

Budget rate generator

£39 – £51 / m
Covers the HB2 kerb units, concrete bed & haunch, the 2-man laying gang and O&P · excl. excavation, sub-base, front paving, drainage, fittings & VAT
Exclusions
  • Excavation, sub-base & formation beneath the kerb — separate groundworks rates (the excavation rate + the Type-1 sub-base family)
  • The carriageway / footway paving in front — bitmac, block paving or slabs (a separate line)
  • Drainage runs, gullies, channels & road gullies
  • Radius / quadrant / drop-kerb fittings, dropped crossings & works beyond a straight run
  • Traffic management / live-carriageway working, road markings, signage & VAT
  • VAT