Budget rate for supply & lay · typical budget rate before your adjustments
Rates are UK national (non-London): central London and constrained urban sites typically run dearer — adjust the labour, plant and access lines in the build-up accordingly.
The supply and laying of SHW Class 6F2 coarse recycled capping / bulk fill (crushed concrete & brick, ~0/75–0/125 mm), spread in layers and compacted to build up levels and form a capping beneath a Type 1 sub-base, priced per m³ of compacted material in place. 6F2 is a coarser, cheaper grade than a Type 1 sub-base, laid in equal-or-thicker lifts. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the delivered 6F2 recycled capping is around 84% of it. Under the settled material route the bought-in bulk fill is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The rate sits at or above a domestic supply-&-lay fill figure because it carries the full main-contractor margin a bill rate needs. That is the expected relationship, not an error. The rate range by material supply:
Budget rate per m³.
Budget rate generator