Budget rate for supply & lay · typical budget rate before your adjustments
Rates are UK national (non-London): central London and constrained urban sites typically run dearer — adjust the labour, plant and access lines in the build-up accordingly.
The supply and placing of C12/15 ready-mixed concrete — the designated GEN2 general-purpose grade used for blinding, oversite, kerb bedding, non-structural floors and mass fill — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. The delivered mix is validated at £96–£117/m³ ex-VAT (ConcreteMath / RMS 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is the low-grade groundworks band of £90–£130/m³, which spans C6/8–C15 and so covers this grade directly; the budget rate sits above it — because it carries the full main-contractor margin the domestic band does not. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator