Budget rate for supply & lay · typical budget rate before your adjustments
Rates are UK national (non-London): central London and constrained urban sites typically run dearer — adjust the labour, plant and access lines in the build-up accordingly.
The supply and placing of GEN1 (C8/10) ready-mixed concrete as mass or trench fill — the low-strength general-purpose grade one step above GEN0, used for oversite, blinding, mass fill and non-structural bases — discharged into the works and hand-placed, tamped and compacted, priced per m³ of concrete placed. This headline is a full-pour, direct-discharge rate: the standard case a groundworks bill prices, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). Even so the figure lands above the £90–£130/m³ a groundworker quotes for supply-and-lay (myjobquote / RMS / ConcreteMath 2026), which is the expected relationship: a main-contractor budget rate sits at or above a domestic supply-and-lay band, and the concrete still carries the main-contractor margin. That is deliberate, not an error — it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator