Facing Brickwork: Standard Stretcher Bond – cost per m² – UK 2026 Rate Guide

Budget rate for supply & lay · typical budget rate before your adjustments

See the full build-up — try free →
Labour, plant, materials, outputs and waste — yours to edit, as an Excel. Three free.

Rates are UK national (non-London): central London and constrained urban sites typically run dearer — adjust the labour, plant and access lines in the build-up accordingly.

Facing brickwork, stretcher bond
per m² · supply & lay
£139 – £240 / m²
What is it

The supply and laying of a half-brick (102.5 mm) skin of standard machine-made facing brickwork in stretcher bond to a vertical wall, priced per m² of wall face. Facing bricks are the exposed outer leaf of a cavity wall, or the visible face of a solid wall — selected, laid to line and gauge, and pointed as the work proceeds. The rate carries two operations:

  1. Laid — facing bricks bedded in mortar to a half-brick stretcher-bond skin, gauged, plumbed and levelled at roughly 60 bricks per m².
  2. Pointed — joints struck and finished as the work proceeds (bucket-handle or weather-struck); a separate finishing pass is not required.
Rate range by wall complexity
Simple£139 – £179 / m²
Standard£158 – £204 / m²
Complex£186 – £240 / m²

Budget rate per m².

3 key cost drivers
Wall complexity
Openings, returns, piers and reveals slow the gang and add cutting waste. It is a key driver of the rate.
Brick type
This rate is for a standard machine-made wirecut facing. Handmade, imperial or reclaimed bricks cost several times more per thousand and are laid more slowly. It is a key driver of material cost.
Location
London and the South East typically add around 20% to labour.
Estimator

Budget rate generator

£158 – £204 / m²
Covers standard facing bricks, bedding mortar, the laying & pointing gang and O&P · excl. prelims, scaffold & VAT
Exclusions
  • Lifting & material distribution — telehandler / forklift, hoist and site-distribution labour (an attendance, in main-contractor prelims)
  • DPC, lintels, wall ties & cavity insulation, movement joints, weep vents & bed reinforcement
  • The inner leaf, cavity insulation & cavity closers
  • Scaffold supply (usually in preliminaries)
  • Preliminaries — main-contractor site set-up, management & welfare
  • VAT