Indicative rates for common construction activities. Use as a reference guide for budgeting, checking tenders, or early-stage estimates.
Granular sub-base, laid & compacted
Blockwork, supply & lay
New rate guides added regularly. Get an email the moment fresh rates go live.
Get updates →Tap any activity to see the full breakdown
The supply and laying of recycled MOT Type 1 granular sub-base, spread in layers and compacted to form the load-bearing base beneath roads, hardstandings, slabs and pavings, priced per m³ of compacted material in place. Recycled Type 1 is crushed and screened from concrete and brick reclaimed from demolition rather than from quarried virgin rock. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
Budget rate per m³.
Budget rate generator
The supply and laying of imported MOT Type 1 granular sub-base, spread in layers and compacted to form the load-bearing base beneath roads, hardstandings, slabs and pavings, priced per m³ of compacted material in place. Virgin Type 1 is crushed straight from quarried rock rather than from recycled demolition arisings, giving a clean, well-graded stone that compacts predictably to a stable platform. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
Budget rate per m³.
Budget rate generator
The supply and laying of Type 3 reduced-fines granular sub-base, spread in layers and compacted to form a load-bearing yet free-draining base beneath SUDS and permeable pavements, tree pits, drainage layers and working platforms, priced per m³ of compacted material in place. Type 3 is the same crushed rock as Type 1 but screened to an open grading with a low fines content, so water drains through it rather than being held in the layer. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
Budget rate per m³.
Budget rate generator
The supply and laying of sub-base, spread in layers and compacted to form the load-bearing base beneath roads, hardstandings, slabs and pavings, priced per m³ of compacted material in place. This guide covers 3 material options, which differ mainly in the delivered stone price and how densely each compacts:
Budget rate per m³
Budget rate generator
The machine excavation of trenches for strip and pad foundations and for buried services, dug with a 13–20 t tracked 360° excavator on a narrow trenching bucket and trimmed by an in-trench banksman, priced per in-situ (bank) m³ of excavated material. This headline is a dig-to-stockpile rate — spoil is cast alongside the trench to re-use as backfill, not carted away. Output, the main driver, is set by the trench context, in three bands:
Budget rate per m³.
Budget rate generator
The supply and laying of a 100 mm nominal (110 mm OD) PVC-u underground drainage run in a prepared trench, on a granular bed with granular surround, jointed and tested, priced per linear metre of pipe run. Trench excavation and disposal of arisings are measured and priced separately (the NRM2 convention) — this rate is the pipe, its bed and its surround. The composite carries two operations:
Budget rate per m³.
Budget rate generator
The supply and laying of a 150 mm nominal (160 mm OD) PVC-u underground drainage run in a prepared trench, on a granular bed with granular surround, jointed and tested, priced per linear metre of pipe run. Trench excavation and disposal of arisings are measured and priced separately (the NRM2 convention) — this rate is the pipe, its bed and its surround. The composite carries two operations:
Budget rate per m³.
Budget rate generator
The supply and placing of GEN0 (C6/8) ready-mixed concrete as mass or trench fill — the low-strength grade used for blinding, backfill and mass foundations — discharged into the works and hand-placed, tamped and compacted, priced per m³ of concrete placed. This headline is a full-pour, direct-discharge rate: the standard case a groundworks bill prices, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 73% of it. On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). Even so the figure lands above the £90–£130/m³ a groundworker quotes for supply-and-lay (myjobquote / RMS / ConcreteMath 2026), which is the expected relationship: a main-contractor budget rate sits at or above a domestic supply-and-lay band, and the concrete still carries the main-contractor margin. That is deliberate, not an error — it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of GEN1 (C8/10) ready-mixed concrete as mass or trench fill — the low-strength general-purpose grade one step above GEN0, used for oversite, blinding, mass fill and non-structural bases — discharged into the works and hand-placed, tamped and compacted, priced per m³ of concrete placed. This headline is a full-pour, direct-discharge rate: the standard case a groundworks bill prices, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). Even so the figure lands above the £90–£130/m³ a groundworker quotes for supply-and-lay (myjobquote / RMS / ConcreteMath 2026), which is the expected relationship: a main-contractor budget rate sits at or above a domestic supply-and-lay band, and the concrete still carries the main-contractor margin. That is deliberate, not an error — it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The machine excavation of reduced levels — stripping a site down to formation for slabs, hardstandings, basements and general bulk dig — with a 13–20 t tracked 360° excavator and a banksman, priced per in-situ (bank) m³ of excavated material. This headline is a dig-to-stockpile rate — spoil is cast to an on-site stockpile for re-use or later removal, not carted away. Output, the main driver, is set by the dig context, in three bands:
Budget rate per m³.
Budget rate generator
The machine strip of the topsoil / vegetable layer at 150–300 mm (150 mm nominal) — clearing a site down to a workable formation for slabs, roads, hardstandings and landscaping — with a 13–20 t tracked 360° excavator and a banksman, heaping the topsoil to an on-site stockpile for re-use, priced per m² of area stripped. This headline is a strip-to-stockpile rate — the topsoil is retained on site, not carted away. Output, the main driver, is set by the access context, in three bands:
Budget rate per m³.
Budget rate generator
The disposal (muck-away) of already-excavated arisings off site to a licensed inert tip — a 13–20 t tracked 360° excavator and banksman loading the stockpiled spoil to grab lorries, which haul and tip it, priced per in-situ (bank) m³ of excavated material. The dig itself is measured and priced separately (the excavation rates); this is the cart-away those rates exclude. The disposal is the bulk of the cost, and the spoil TYPE sets it — loose spoil bulks as it is dug, and the tip is paid on the loose (carted) volume, in three bands:
Budget rate per m³.
Budget rate generator
The supply and placing of C20/25 ready-mixed concrete — the designated foundation grade (RC20/25 / FND2 / ST4) used for mass and lightly-reinforced foundations, footings, ground beams and ground-bearing slabs — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. The delivered mix is validated at £100–£125/m³ ex-VAT (ConcreteMath / RMS / Mister Concrete 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³; a designated C20/25 foundation rate sits above it — for the richer mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C25/30 ready-mixed concrete — the general structural / reinforced grade (designated RC25/30) used for reinforced foundations, ground beams, pile caps, ground-bearing slabs and general RC work — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 74% of it. The delivered mix is validated at £105–£135/m³ ex-VAT (ConcreteMath / Mister Concrete / RMS 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³ (a lower-grade reference); a designated C25/30 structural rate sits above it — for the richer mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C30/37 ready-mixed concrete — the standard structural / reinforced-concrete grade (designated RC30/37) used for footings, ground beams, suspended and ground-bearing slabs, columns and walls — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 75% of it. The delivered mix is validated at £110–£142/m³ ex-VAT (ConcreteMath / RMS / Mister Concrete 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³ (a lower-grade reference); a designated C30/37 structural rate sits above it — for the richer mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C16/20 ready-mixed concrete — the designated GEN3 general-purpose grade used for oversite, footings, mass and lightly-loaded foundations and non-structural ground-bearing slabs — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. The delivered mix is validated at £98–£120/m³ ex-VAT (ConcreteMath / RMS 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³; a designated C16/20 general-purpose foundation rate sits above it — for the mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C12/15 ready-mixed concrete — the designated GEN2 general-purpose grade used for blinding, oversite, kerb bedding, non-structural floors and mass fill — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 72% of it. The delivered mix is validated at £96–£117/m³ ex-VAT (ConcreteMath / RMS 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is the low-grade groundworks band of £90–£130/m³, which spans C6/8–C15 and so covers this grade directly; the budget rate sits above it — because it carries the full main-contractor margin the domestic band does not. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C35/45 ready-mixed concrete — the high-strength structural grade (designated RC35/45) used for heavily-loaded and durability-critical foundations, ground beams, transfer slabs, columns and precast / prestressed work above C30/37 — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 76% of it. The delivered mix is validated at £118–£145/m³ ex-VAT (ConcreteMath / RMS / Mister Concrete 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³ (a much lower-grade reference); a designated C35/45 high-strength structural rate sits well above it — for the far richer mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C40/50 ready-mixed concrete — the high-strength structural grade (designated RC40/50) used for heavily-loaded and durability-critical foundations, ground beams, transfer slabs, water-retaining structures and precast / prestressed work above C35/45 — discharged into the works and placed, tamped and compacted, priced per m³ of concrete placed. This headline prices the concrete on the standard mass / trench-fill placing output: the place-level-vibrate operation is the same whatever the grade, and formwork and reinforcement are separately measured items. It is a full-pour, direct-discharge rate, with pumping, part loads and barrowed delivery as the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the ready-mixed concrete is around 77% of it. The delivered mix is validated at £125–£150/m³ ex-VAT (ConcreteMath / RMS / Mister Concrete 2026, national supply-only). On a main-contractor budget rate the bought-in ready-mix is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The nearest published supply-and-lay benchmark is a low-grade groundworks figure of £90–£130/m³ (a much lower-grade reference); a designated C40/50 high-strength structural rate sits well above it — for the far richer mix, and because it still carries the main-contractor margin. That is the expected relationship, not an error: it is where a QS pricing sublet concrete at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and placing of C32/40 (designated RC32/40) structural ready-mixed concrete to a SUSPENDED slab — pumped into prepared formwork, vibrated, tamped and floated to level, priced per m³ of concrete placed. This is a structural-FRAME element, not a groundworks pour: it is the concrete a QS prices for suspended floor slabs, transfer slabs and elevated decks, placed around the reinforcement in the formed slab and finished ready to receive a screed or floor finish. Formwork and reinforcement are separately measured items. It is a full pumped-pour rate; part loads, standing time and barrowed delivery are the variants below.
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate for a SUBLET frame-package element, and the C32/40 ready-mixed concrete is around 74% of it. The delivered mix is validated at £114–£143/m³ ex-VAT (interpolated between the live C30/37 and C35/45 grades and corroborated by ConcreteMath’s direct national C32/40 range). Unlike the groundworks concrete grades — which the main contractor orders on its own account, so their ready-mix carries the main-contractor O&P only — a suspended structural slab is bought AND placed by a specialist concrete-frame subcontractor, so the whole rate (concrete included) carries the full fee-on-fee ladder: the +5% market, the +20% sub-contractor O&P and the +20% main-contractor O&P for sublet work. The nearest published supply-and-place reference is a domestic figure of £85–£120/m³ (small-job, no fee-on-fee and no floated finish); a sublet main-contractor budget rate for a suspended slab sits well above it — for the sublet fee-on-fee and the slower, finished, elevated placing. That is the expected relationship, not an error: it is where a QS pricing a concrete frame at main-contract level needs the rate to sit. The rate range, low to high:
Budget rate per m³.
Budget rate generator
The supply and laying of a BS EN 1340 HB2 half-battered precast-concrete kerb (125×255×914 mm), set out to line and level on a ~100 mm concrete bed and backed with a concrete haunch to about two-thirds of the kerb height, priced per linear metre of finished straight kerb run. This is the standard external-works kerbing line on UK bills of quantities. The composite carries two operations:
Budget rate per m³.
Budget rate generator
The supply and laying of SHW Class 6F2 coarse recycled capping / bulk fill (crushed concrete & brick, ~0/75–0/125 mm), spread in layers and compacted to build up levels and form a capping beneath a Type 1 sub-base, priced per m³ of compacted material in place. 6F2 is a coarser, cheaper grade than a Type 1 sub-base, laid in equal-or-thicker lifts. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the delivered 6F2 recycled capping is around 84% of it. Under the settled material route the bought-in bulk fill is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The rate sits at or above a domestic supply-&-lay fill figure because it carries the full main-contractor margin a bill rate needs. That is the expected relationship, not an error. The rate range by material supply:
Budget rate per m³.
Budget rate generator
The supply and laying of SHW Class 1A imported general granular fill (recycled well-graded crushed hardcore, ~0/80–0/125 mm), spread in layers and compacted to build up levels and form general / embankment fill, priced per m³ of compacted material in place. Class 1A is the lower-grade general-fill class laid beneath a capping or sub-base. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
A note on the number, for estimators: this is a MAIN-CONTRACTOR budget rate, and the delivered Class 1A recycled fill is around 82% of it. Under the settled material route the bought-in bulk fill is ordered on the contractor’s own account, so it carries the main-contractor O&P only — it is NOT marked up with the market +5% or the sub-contractor O&P +20% (those fall on the laying gang, which does carry the full ladder). The rate sits at or above a domestic supply-&-lay fill figure because it carries the full main-contractor margin a bill rate needs. That is the expected relationship, not an error. The rate range by material supply:
Budget rate per m³.
Budget rate generator
The supply and laying of SHW Class 6N selected granular fill (recycled well-graded crushed hardcore, ~0/80 mm), spread and compacted as selected backfill to concrete structures and behind retaining walls, priced per m³ of compacted material in place. Class 6N is a selected fill placed to a tighter compaction than loose general fill. Material supply sets the delivered stone price, which is the bulk of the rate, and comes in three bands:
A note on the number, for estimators: this rate is identical to our Class 1A general fill by construction, not by a manufactured uplift. In the priced recycled market Class 6N and Class 1A are the SAME well-graded crushed-hardcore stock (~2.0 t/m³) — merchants publish “6N” pages quote-only, with no separate recycled 6N uplift — so 6N is priced off the same representative row and lands on the same headline. This is a MAIN-CONTRACTOR budget rate: the delivered fill is around 82% of it and, under the settled material route, carries the main-contractor O&P only (the laying gang carries the full ladder). A PRIMARY / virgin 6N, if ever priced separately, would be a distinct rate. The rate range by material supply:
Budget rate per m³.
Budget rate generator
The supply and fixing of loose high-yield steel reinforcement bar (BS 4449 grade B500B), cut, bent and delivered to a bending schedule, then placed, tied, lapped and supported on spacers and chairs to reinforce foundations and slabs, priced per tonne of bar supplied and fixed — the way a bill of quantities measures reinforcement. This headline prices a general foundations / ground-slab schedule (predominantly 12–25 mm bar). The rate carries two operations:
Budget rate per m³.
Budget rate generator
The supply, fabrication and erection of a structural steel frame — universal beams and columns (UB/UC), cut, drilled and welded with their connections and a shop primer coat, delivered to site and then crane-lifted, plumbed, bolted up and aligned into the building frame, priced per tonne of erected steelwork — the way a bill of quantities measures structural steel. This headline prices a general commercial / industrial frame of mixed piece weights. The rate carries two operations:
Budget rate per m³.
Budget rate generator
Tap any activity to see the full breakdown
The supply and laying of a single skin of 100 mm aircrete (autoclaved-aerated-concrete) blockwork of 3.6 N/mm² grade, priced per m² of wall face. Aircrete is the lightest walling block, full of trapped air, so it lays fast, cuts easily and insulates well, and the 3.6N grade is the standard strength for the inner leaf of a cavity wall and for partitions. Two jointing systems cover most jobs:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm aircrete blockwork of 7.3 N/mm² grade, priced per m² of wall face. Aircrete is the lightest walling block, full of trapped air, so it lays fast, cuts easily and insulates well, and the 7.3N grade is the high-strength version, carrying load for a load-bearing inner leaf or partition. Two jointing systems cover most jobs:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm dense aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. Dense aggregate blocks are the strongest and hardest-faced 100 mm block, used for load-bearing, below-DPC and party walls where a durable face matters. Two block finishes are priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm lightweight-aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. Lightweight-aggregate blocks are lighter and more thermally efficient than dense block but harder-faced than aircrete, and the 7.3N grade is load-bearing. Two block finishes are priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm medium-density aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. Medium-density blocks sit between dense and aircrete: lighter than dense and load-bearing at 7.3N. Two block finishes are priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm blockwork, priced per m² of wall face, across the five block types that cover most UK projects. The five types are:
Budget rate per m².
Budget rate generator
The supply and laying of a half-brick (102.5 mm) skin of standard machine-made facing brickwork in stretcher bond to a vertical wall, priced per m² of wall face. Facing bricks are the exposed outer leaf of a cavity wall, or the visible face of a solid wall — selected, laid to line and gauge, and pointed as the work proceeds. The rate carries two operations:
Budget rate per m².
Budget rate generator
The supply and laying of a half-brick (102.5 mm) skin of Class B engineering brickwork below the damp-proof course to a vertical substructure wall, priced per m² of wall face. Below-DPC brickwork is the buried or ground-level masonry beneath the DPC — Class B engineering bricks are specified for their low water absorption and high compressive strength where the wall sits in damp, aggressive ground. The rate covers:
Budget rate per m².
Budget rate generator
The supply and laying of a full cavity wall as one composite rate, priced per m² of wall face: a half-brick (102.5 mm) facing outer leaf in stretcher bond, a full-fill insulated cavity with wall ties, and a 100 mm block inner leaf — the standard external wall of a UK masonry building. The rate builds all three elements as one gang operation:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 100 mm smooth-faced (paint-grade) blockwork to a vertical wall, priced per m² of wall face. Paint-grade blocks carry a smooth, close-textured face laid to a finished line so the wall can be sealed and painted directly — no plaster or render coat is needed. Three block specifications are priced:
Budget rate per m².
Budget rate generator
The supply and laying of a 75 mm nominal traditional sand:cement (1:4, sharp sand) floor screed, site-batched in a mixer and ruled to level over a structural base to receive a floor finish, priced per m² of finished floor. A screed is the levelling topping between the structural slab and the floor finish — not the structural base itself. The rate carries two operations:
Budget rate per m².
Budget rate generator
The supply and fixing of 12.5 mm tapered-edge plasterboard, dot-and-dabbed (adhesive-fixed) to a blockwork or masonry background and finished with a 2–3 mm multi-finish skim to receive decoration, priced per m² of finished wall. This is the standard internal drylining line — the board and skim, not the background wall behind it, which is a separate rate. The composite carries two operations:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm dense aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. At 140 mm the dense aggregate block gives a thicker, heavier leaf than the 100 mm skin — specified for higher loadings, party and separating walls, and below-DPC substructure where mass, strength and a durable face matter. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm medium-density aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. The medium-density 140 mm block is a lighter, better-insulating unit than the dense block at the same thickness — the common choice for load-bearing inner leaves and party walls where thermal and acoustic performance matter as well as strength. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a 150 mm ground-bearing floor slab, priced per m² of slab: a 1200-gauge polythene damp-proof membrane, A193 steel-fabric reinforcement mesh and C28/35 ready-mixed structural concrete, placed, tamped, screeded and floated to level over a prepared sub-base — the standard ground floor of a UK building, the concrete element measured per m². The rate builds the slab as one gang operation:
Budget rate per m².
Budget rate generator
The supply and laying of a nonwoven separation geotextile — a Terram 1000-class filtration fabric — rolled out and lapped over a prepared formation, priced per m² of membrane. The membrane is the separation layer between the soft subgrade and the granular sub-base above it: it stops the subgrade fines pumping up into the stone and the stone punching down into soft ground, so the sub-base keeps its load-bearing thickness. The rate carries two operations:
Budget rate per m².
Budget rate generator
The construction of a new bituminous macadam (tarmac) footway, priced per m² of finished path: the formation trimmed to level, a ~150 mm compacted MOT Type 1 granular sub-base, and a ~65 mm bituminous macadam surfacing — a binder course under a wearing course — laid and rolled over it. This is the standard external-works footpath line on a UK BoQ; edgings and kerbs are measured separately (a linear item). The rate builds the footway as three operations by one gang:
Budget rate per m².
Budget rate generator
The making, fixing and striking of traditional 18 mm ply-and-timber formwork — the temporary mould an in-situ concrete slab is cast against — to the SOFFIT (underside) and EDGES of the slab, priced per m² of CONTACT (formed) face, the way a bill of quantities measures formwork. The forms are cut and assembled from shuttering plywood on softwood bearers, carried on adjustable steel props, oiled with release agent, then STRUCK, cleaned and removed once the concrete has gained strength — a temporary works item, not left in the slab. This headline prices a basic (F1) soffit finish. The rate carries three operations by one carpentry gang:
Budget rate per m².
Budget rate generator
The construction of a freestanding non-loadbearing internal PARTITION on a light-gauge galvanised metal frame — 70 mm ‘C’ studs at 600 mm centres in ‘U’ head & floor tracks — with a 25 mm acoustic mineral-wool quilt pushed into the stud cavity, 12.5 mm tapered-edge plasterboard screw-fixed to BOTH faces and a 2–3 mm multi-finish skim to each face, priced per m² of finished partition. One m² of partition carries two boarded & skimmed faces plus the shared frame and quilt. This is the standard fit-out internal-walling line — the whole wall, not a lining applied to an existing background (that is a separate rate). The rate carries four operations by one drylining gang:
Budget rate per m².
Budget rate generator
The supply and laying of a 50 mm nominal pumped calcium-sulphate (anhydrite) liquid flowing floor screed, delivered ready-mixed and pumped to place, laid unbonded/floating over a prepared base to receive a floor finish, priced per m² of floor. A liquid screed is the self-levelling levelling topping between the structural base and the floor finish — the fast, pumped alternative to a traditional sand:cement screed. The rate carries two operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a pitched-roof covering of large-format concrete interlocking tiles (~10 tiles/m²), laid on a breathable underlay and treated battens and fixed per BS5534, priced per m² of roof slope. Concrete interlocking tiles are the mainstream UK budget pitched-roof covering — large tiles that lock together, laying fast with few tiles per m². The rate carries three operations:
Budget rate per m².
Budget rate generator
The construction of one precast concrete-ring man-entry manhole — a 1200 mm diameter chamber roughly 2.0 m deep to invert, set complete and priced per nr (each). A manhole is the access & junction chamber a drainage BoQ measures separately from the pipe runs. The rate carries the whole operation:
Budget rate per m².
Budget rate generator
The supply and application of a through-coloured monocouche one-coat render (Weber Pral M / K Rend K Mono class), mixed, applied 15–20 mm and scraped to a textured finish over a blockwork or masonry background, priced per m² of rendered wall. This is the standard external render finish — the render coat, not the wall behind it, which is a separate rate. For an all-in rendered blockwork wall, add this to the plain blockwork rate; the internal equivalent is plasterboard on dot-and-dab. The finish carries:
Budget rate per m².
Budget rate generator
The supply and installation of a full external wall insulation (EWI) system to an existing solid or masonry wall, priced per m² of insulated & rendered wall. This is the standard, mainstream EWI spec — a 100 mm graphite-EPS insulation board finished with a through-coloured silicone thin-coat render. A mineral-wool board system (fire-rated / breathable) is the dearer alternative. The system carries four operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a fully-adhered single-ply EPDM rubber flat-roof covering — the waterproofing membrane, its deck & contact adhesive and the perimeter trims & sundries — bonded to a prepared deck, priced per m² of flat-roof area. EPDM single-ply is the mainstream UK domestic & light-commercial flat-roof covering, the modern one-piece replacement for built-up felt. This rate prices the COVERING only — the deck, vapour-control layer and insulation (the warm-roof build-up) are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a first-fix timber floor structure — C24 softwood floor joists set out, hung and fixed to gauge with mid-span strutting/blocking, joist hangers, lateral restraint straps and fixings — priced per m² of floor area. C24 solid joists at ~400 mm centres are the mainstream UK budget timber floor carcass. This rate prices the STRUCTURE only — the floor decking (chipboard/ply/T&G), the insulation between joists and any second-fix carpentry are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a structural floor deck — 22 mm P5 moisture-resistant tongue-&-groove chipboard flooring cut, glued at the T&G joints and screwed/nailed down over prepared first-fix joists to a level braced deck — priced per m² of floor area. 22 mm P5 T&G chipboard is the mainstream UK budget floor deck; it is the board that completes the first-fix timber floor the joists carry. This rate prices the DECK only — the joists it sits on, the insulation and any screed or floor finish are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and installation of a composite (WPC) wood deck — wood-plastic-composite deck boards laid on hidden clips to falls over a treated softwood subframe (joists at ~400 mm centres, bearers and posts/pads) and a weed-control membrane, on prepared level ground — priced per m² of deck area. A capped solid WPC board is the mainstream UK garden deck; low-maintenance, splinter-free and far longer-lived than a softwood deck. This rate prices the DECK only — balustrade, steps, foundations and drainage are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a warm-roof build-up — an 18 mm OSB3 structural deck laid over the roof structure, a self-adhesive vapour control layer lapped and bonded over it, and rigid PIR flat-roof insulation boards cut, bonded and fixed to a level braced substrate ready to receive the waterproofing covering — priced per m² of roof area. The warm-roof build-up is Building-Regs-driven on essentially every modern flat roof; it is the substrate that sits UNDER the single-ply / felt / GRP covering. This rate prices the BUILD-UP only — the covering over it, the roof structure below it and the rainwater goods are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The construction of one precast concrete trapped ROAD gully — a 450 mm diameter, 750 mm deep (70 L) gully pot with a Class D400 ductile grating & frame, set complete and priced per nr (each). A road gully is the trapped surface-water inlet a drainage BoQ measures separately from the pipe runs. The rate carries the whole operation:
Budget rate per m².
Budget rate generator
The supply and fixing of an insulated laminate (thermal-board) dry lining to a masonry background — a 62.5 mm board (50 mm rigid PIR insulation factory-bonded to a 12.5 mm tapered-edge plasterboard face) dot-and-dabbed to the wall, pinned back with secondary mechanical fixings, taped and finished with a 2–3 mm multi-finish skim — priced per m² of wall. Insulated laminate boards are the mainstream way to thermally upgrade a solid or under-performing masonry wall from the inside without building a separate frame. This rate prices the DABBED lining to a sound masonry wall — the freestanding/independent (battened or metal-framed) lining used on a damp or uneven wall is a separate build. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a second-fix softwood skirting run — softwood (redwood) torus/ogee skirting measured, cut, mitred at internal & external corners, scribed to the floor and fixed (grab adhesive plus pins or screws) to masonry or studwork, with caulk & filler to finish — priced per metre of run. A 25 × 125 mm softwood torus/ogee board is the mainstream UK budget skirting. The calculator also prices the two sibling second-fix mouldings run the same way — softwood architrave to door & opening surrounds and softwood/MDF window board to reveals (different sections and outputs, so different BoQ rates); internal doors & ironmongery and staircases are separate rates, and the decoration is a painter’s rate. The skirting run carries three operations:
Budget rate per m².
Budget rate generator
The supply and installation of a linear (slot / “ACO-type”) channel drain — a ~100 mm internal-width, Class D400 (trafficked, 40 t) channel supplied complete with its ductile-iron slotted grating, set to falls in a concrete surround and priced per linear metre. A linear channel drain is the surface-water interceptor a civils BoQ measures separately as “gullies & channels”. The rate carries the whole operation:
Budget rate per m².
Budget rate generator
The construction of an INDEPENDENT (freestanding) dry lining to an existing wall on a light-gauge galvanised metal frame stood OFF the wall — 70 mm ‘C’ studs at 600 mm centres in ‘U’ head & floor tracks, tied back to the wall — with a 25 mm mineral-wool quilt in the frame cavity, 12.5 mm tapered-edge plasterboard screw-fixed to the ONE (room) face and a 2–3 mm multi-finish skim to that face, priced per m² of lining. An independent lining is used where the wall behind is damp, uneven or out of plumb and a dot-and-dab will not adhere, or where a ventilated cavity or a thermal / acoustic upgrade is wanted — the frame stands the new face clear of the wall. It differs from a dabbed lining (stuck to the wall) and from a metal-stud partition (a freestanding wall with two boarded faces). The rate carries four operations by one drylining gang:
Budget rate per m².
Budget rate generator
The supply and hanging of an internal door — a standard door leaf trimmed and planed to fit a prepared lining, hung on 1.5 pairs of butt hinges with a morticed tubular latch and lever-on-rose furniture, then eased, adjusted and hung to swing and latch cleanly — priced per door (nr). A moulded 4/6-panel white-primed leaf is the mainstream UK budget internal door. This rate prices the DOOR only — the door lining/frame, the architrave, the decoration and any glazing or closers are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and application of emulsion decoration to plastered walls & ceilings — light prep & filling of minor defects, cutting in to edges, reveals & ceiling lines, a thinned mist coat to seal new or prepared plaster and two full coats of vinyl-matt emulsion, roller-applied — priced per m² of finished surface. Trade vinyl matt is the mainstream UK budget wall & ceiling emulsion. This rate prices the EMULSION to walls & ceilings only — the joinery gloss, external decoration, spray application and wallpaper are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and laying of a 40 mm asphalt surface course (wearing course) as a machine-laid overlay to a prepared, structurally-sound carriageway, priced per m² of finished surface. A sprayed tack (bond) coat, then the surface course laid to line & level by the paver and compacted by the roller. This rate prices the wearing-course overlay ONLY — the binder course beneath, planing of the old surface, kerbs, ironwork, markings and traffic management are separate items. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and laying of a ~90 mm asphalt carriageway resurface — a ~60 mm AC20 binder course under a ~30 mm AC10 (or SMA) surface course, machine-laid in two passes to a prepared, structurally-adequate base — priced per m² of finished road. Tack/bond coats bond the base and the interlayer; both courses are laid to line & level by the paver and rolled to density. This rate prices the binder + surface resurface ONLY — planing/excavation of the old road, kerbs, ironwork, markings and traffic management are separate items. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and laying of a ~50 mm AC20 binder / regulating course, machine-laid in a single pass to a prepared, structurally-adequate base, priced per m² of finished course. A sprayed tack (prime) coat, then the binder course laid to line & level by the paver and compacted by the roller — used to regulate and level a base before the surface course, or as a strengthening base course. This rate prices the binder / regulating course ONLY — the surface (wearing) course on top, planing of the old road, kerbs, ironwork, markings and traffic management are separate items. The rate carries three operations:
Budget rate per m².
Budget rate generator
The cold planing (milling) of the existing bituminous road surface, priced per m² of planed area. A half-lane (~1 m) cold planer mills off the worn surface to depth in a single pass so a fresh binder or surface course can be laid back. This rate prices the planing / milling operation ONLY — the arisings (road planings) are a recycled resource carted away separately, and the binder / surface courses laid back on the planed base, kerbs, ironwork, road markings and traffic management are all separate items. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and application of a ~100 mm continuous thermoplastic (hot-applied screed) road-marking line to a prepared, sound carriageway surface, priced per metre of line. A road-marking gang melts the thermoplastic screed in the pre-melt boiler and applies it to line with the screed applicator, dropping glass beads onto the hot material for reflectivity. This rate prices the supply & application of the continuous line ONLY — surface preparation, pre-marking / setting-out survey, removal of old lines, reflective studs, arrows, letters, symbols & hatching, and the carriageway courses laid or planed are all separate items. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a bought-in manufactured straight staircase flight — a closed-string softwood/MDF flight (around 13 risers to suit a standard floor-to-floor, treads and risers, with the newels, handrail and spindles supplied with a standard flight) offered up to a prepared, trimmed opening, the strings cut and scribed to the trimmer and wall, the flight levelled, wedged and glue-blocked, fixed off and made good — priced per flight (nr). A mainstream softwood/MDF straight flight is the UK budget default. This rate prices the FLIGHT supplied and fixed only — the structural trimming of the opening, the strip-out of an existing stair, the balustrade to landings and the finishes and decoration are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and application of gloss decoration to softwood joinery — skirting, architrave, doors & frames — with knots spot-treated, the timber primed, undercoated and finished with one-to-two coats of gloss or satinwood, brush-applied and de-nibbed between coats, priced per metre of run. A trade undercoat plus a quick-dry gloss or satinwood is the mainstream UK budget joinery finish. This rate prices the JOINERY gloss only — the emulsion to walls & ceilings, external decoration, spray application and wallpaper are separate rates, and the joinery itself is supplied & fixed by the carpentry rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of an internal door lining / casing set — the timber set (two jambs and a head, with loose planted stops) that lines a structural door opening and onto which the door leaf is later hung — offered up to a prepared opening, both jambs plumbed true, packed and shimmed to line, fixed off, the loose stops pinned and made good — priced per opening (nr). A mainstream softwood or MDF lining set is the UK budget default. This rate prices the LINING only — the door leaf, the ironmongery, the architrave and the decoration are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a staircase balustrade — the guarding to the open side of a flight and to landings and galleries: newels set and plumbed, base rail and handrail cut to the rake between the newels, and softwood spindles measured, cut top and bottom to the rake, drilled, pinned and spaced to the Building-Regs 100 mm sphere rule (around seven spindles per metre of run) — priced per metre of run. A mainstream softwood spindle balustrade is the UK budget default; a plainer wall-mounted handrail run is the lower end and an oak or hardwood turned-spindle balustrade the dearer. This rate prices the BALUSTRADE RUN supplied and fixed only — the manufactured flight itself, the structural trimming of the opening, the strip-out of an existing balustrade and the finishes and decoration are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and application of exterior decoration to rendered & masonry walls, fascias & soffits on a masonry substrate — a fungicidal wash & treatment of organic growth, filling & making good of minor cracks & defects, cutting in to edges, verges, reveals & features, and two full coats of exterior masonry paint, roller & brush-applied — priced per m² of finished surface. Trade smooth masonry paint is the mainstream UK budget exterior coating. This rate prices the EXTERNAL MASONRY decoration only — the external joinery gloss, interior emulsion & joinery gloss, spray application and wallpaper are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
Raising and re-bedding an existing gully grating or manhole / chamber cover & frame to a new surface level after a carriageway resurface, priced per adjusted frame (nr). A highways gang saw-cuts and breaks out the existing surround, lifts the existing frame, rebuilds the seating on one to two courses of engineering brick bedded to the new level, then re-beds and haunches the EXISTING frame on rapid-set mortar and makes good. This rate ADJUSTS the existing ironwork ONLY — supplying a new cover, frame or precast chamber is a separate set-complete item, and the connecting drainage run, the carriageway courses laid or planed, road markings and traffic management are all separate items too. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and application of a full weatherproof decoration to external softwood joinery — fascias, bargeboards, external doors & frames — with knots spot-treated, the timber primed, undercoated and finished with one to two coats of exterior gloss or wood stain, brush-applied and de-nibbed between coats, priced per metre of run. A trade exterior gloss or 10-year woodstain is the mainstream UK budget system. This rate prices the EXTERNAL JOINERY decoration only — the external masonry & render decoration, interior emulsion & joinery gloss, spray application and wallpaper are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a new uPVC roofline & rainwater-goods run to the eaves — fascia, soffit & bargeboard boards fixed to the rafter feet and eaves overhang, a 112 mm half-round gutter run to falls on brackets, and a 68 mm downpipe fixed with clips & shoe — priced per metre of eaves run. uPVC roofline is the mainstream UK budget system: maintenance-free boards and rainwater goods to the perimeter every pitched roof terminates against. This rate prices the roofline SUPPLY & FIX only — the roof structure, the roof covering & its linear details, the decoration of the fascia and the scaffold are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and hanging of a wall covering — lining paper or a finish wallpaper — to sound, prepared, sized plastered walls & ceilings, priced per m² of finished surface. The paper-hanger sizes the wall, sets out and plumbs, cuts and pastes (or pastes the wall), hangs the covering with matched seams, rolls the seams and trims top & bottom to a clean finish. A single hang of a mid-range paper to a sound wall is the mainstream UK budget line. This rate prices the WALL COVERING only — the plaster background, stripping of existing paper, cross-lining, and the emulsion & joinery-gloss decoration of the same room are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of new milled lead flashings and details where the roof meets an abutment, chimney, verge or valley — cover, stepped and apron flashings dressed to the masonry with the upstand wedged and pointed into the chase, lead soakers laid under the roof covering at ridge, hip and verge lines, and lead valley gutters formed and bossed to falls — priced per metre of flashing run. Milled lead (Code 4/5) is the traditional durable weathering material: maintenance-free, a 100-year-plus life, easily worked to complex details. This rate prices the leadwork SUPPLY & FIX only — the roof structure, the roof covering & its field / linear details, the roofline & rainwater goods, and the scaffold are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and fixing of a pitched-roof structural carcass — prefabricated trussed rafters (Fink) or a traditional site-cut roof of rafters, ridge, purlins and ceiling ties, with the wall plates seated & levelled, diagonal & longitudinal bracing, tilting fillets and galvanised lateral & holding-down restraint straps, set out, lifted, plumbed, braced & fixed to the engineer’s layout — priced per m² of roof plan (footprint) area. This is the roof STRUCTURE the covering, roofline & leadwork all sit on. This rate prices the structural carcass SUPPLY & FIX only — the roof covering & its details, the roofline & rainwater goods, the leadwork & flashings, insulation and the scaffold are separate rates. The rate carries three operations:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm dense aggregate blockwork of 10.4 N/mm² grade to a vertical wall, priced per m² of wall face. At 10.4 N/mm² this is the high-strength engineering-grade dense block — specified for heavily-loaded piers, party and separating walls and below-DPC substructure where maximum load capacity and a durable face are needed. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm aircrete (autoclaved aerated) blockwork of 3.6 N/mm² grade to a vertical wall, priced per m² of wall face. The aircrete block is a lightweight thermal AAC unit — the common choice for insulating inner leaves and internal load-bearing walls where thermal performance and fast single-hand laying matter. Laid here on traditional sand-cement mortar. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm aircrete (autoclaved aerated) blockwork of 7.3 N/mm² high-strength grade to a vertical wall, priced per m² of wall face. A high-strength thermal AAC block for load-bearing inner leaves and party walls that need both insulation and strength — the dearest block in the 140 mm family. Laid on traditional sand-cement mortar. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm lightweight-aggregate blockwork of 3.6 N/mm² grade to a vertical wall, priced per m² of wall face. A lightweight expanded-clay aggregate block (Plasmor Fibolite class) — specified for insulating inner leaves and partitions where a lighter, better-insulating unit than dense aggregate is wanted. Laid on traditional sand-cement mortar. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 140 mm lightweight-aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. A load-bearing lightweight expanded-clay aggregate block — for inner leaves and party walls that want the strength of a 7.3 N unit with lighter weight and better insulation than dense aggregate. Laid on traditional sand-cement mortar. One finish is priced:
Budget rate per m².
Budget rate generator
The supply and laying of a single skin of 215 mm SOLID dense aggregate blockwork of 7.3 N/mm² grade to a vertical wall, priced per m² of wall face. At 215 mm the solid dense block is the thickest, heaviest unit in the range — a full solid block (a two-man lift) for heavily-loaded and acoustic separating walls where mass and strength matter most. One finish is priced:
Budget rate per m².
Budget rate generator