Free construction rate guide

How much does it cost to build?

Indicative rates for common construction activities. Use as a quick reference for budgeting, checking tenders, or early-stage estimates.

Civil engineering

Excavation, earthworks, drainage, roads, concrete structures and groundworks.

10 activities  
🏗

Buildings

Tiling, blockwork, plastering, screeding, painting, ceilings and partitions.

10 activities  

Civil engineering rates

Tap any activity to see the full breakdown

Excavation
per m³
£15 – £200 / m³
What is it

Excavation is the removal of earth, rock, or other material from a site. The rate covers labour and plant to dig and dispose of material. It is one of the most variable items in construction — the same unit price question can yield £15/m³ for bulk machine excavation on an open site, or £200/m³ for hand excavation in a confined space around live services. Without knowing the specifics, a QS has no choice but to be conservative.

Rate range
Cheap
£15 – £35 / m³
Typical
£35 – £90 / m³
High
£90 – £200 / m³

Labour and plant only in GBP. Excludes disposal, prelims, overhead & profit.

3 key cost drivers
Method of excavation
Machine excavation on an open site is fast and cheap. Hand excavation in a restricted space around services is slow and expensive.
Ground conditions
Soft or loose material is easy to shift. Firm, compacted, or rocky ground takes far longer and may need specialist plant or blasting.
Site constraints
Restricted access, trench support, working around live services, and small quantities all reduce productivity and push rates up.
Estimator

Labour and plant budgeting guide only — not a tender price.

£45 – £75 / m³
Labour and plant only · excl. disposal, prelims, O&P
Exclusions
  • Preliminaries (site setup, supervision, welfare)
  • Contractor overhead and profit
  • Disposal / haulage of excavated material
  • Imported backfill or filling material
  • Trench support and shoring
  • Dewatering and groundwater control
  • Service diversions or protection
  • Rock breaking or blasting
  • VAT
🔧
Trench excavation
per m³
£25 – £200 / m³
What is it

Trench excavation is the digging of narrow, linear trenches for drainage, foundations, or underground services. Unlike bulk excavation, productivity is limited by trench width — plant cannot work as freely, and depth increases risk significantly. The rate covers excavation only; trench support, backfill, and disposal are all separate. Depth is the single biggest cost driver because deeper trenches require shoring, slower working, and different plant.

Rate range
Cheap
£25 – £45 / m³
Typical
£45 – £100 / m³
High
£100 – £200 / m³

Labour and plant only in GBP. Excludes trench support, backfill, disposal, prelims, overhead & profit.

3 key cost drivers
Depth
Shallow trenches (<1.5m) are quick. Trenches over 1.5m require shoring, slower working speeds and different plant — costs scale sharply with depth.
Ground conditions
Soft ground is fast and easy. Hard or rocky ground needs breaking. Running sand or groundwater adds dewatering cost on top of slower excavation.
Method
Machine trenching is far faster than hand digging. Where services are present, hand trimming adds significant time even when machines do the bulk of the excavation.
Estimator

Labour and plant budgeting guide only — not a tender price.

£48 – £85 / m³
Labour and plant only · excl. trench support, backfill, disposal, prelims, O&P
Exclusions
  • Trench support and shoring (priced separately)
  • Disposal / haulage of excavated material
  • Imported granular backfill or reinstatement
  • Dewatering and groundwater management
  • Service identification and protection
  • Rock breaking (priced separately)
  • Preliminaries, overhead and profit
  • VAT
🏗
RC concrete
per m³ all-in
£300 – £1,200 / m³
What is it

Reinforced concrete (RC) is concrete poured around steel reinforcement bars to create structural elements — walls, columns, beams, slabs and foundations. This all-in rate covers concrete supply, rebar supply and fixing, formwork supply and striking, and concrete placement including pump. It is one of the most variable items in construction estimating. The same m³ question could yield £300/m³ for a simple pad or £1,200/m³ for a complex heavily reinforced element in a restricted location.

Rate range
Cheap
£300 – £420 / m³
Typical
£420 – £700 / m³
High
£700 – £1,200 / m³

All-in rate (concrete + rebar + formwork + placement) in GBP. Excludes prelims, overhead & profit.

3 key cost drivers
Rebar density
A simple pad might have 40 kg of rebar per m³. A heavily loaded column could exceed 250 kg/m³. At £1,200–1,600/tonne supply and fix, rebar density alone can double the rate.
Formwork complexity
Flat slab formwork on a large repetitive area is cheap. Complex bespoke formwork for curved or non-standard elements is expensive to make, erect and strike — and can only be used once.
Pour size and access
A large pour amortises pump, labour and setup cost across many m³. A small pour in a restricted location has high fixed costs and low output — pushing the per-m³ rate up sharply.
Estimator

All-in budgeting guide only — not a tender price.

£480 – £720 / m³
Standard RC element · all-in (concrete + rebar + formwork + placement) · excl. prelims, O&P
Exclusions
  • Excavation to formation level
  • Blinding concrete (priced separately)
  • Waterproofing membranes or tanking
  • Concrete testing and trial mixes
  • Post-tensioning or pre-stressing
  • Concrete finishes beyond standard tamped/floated
  • Preliminaries, overhead and profit
  • VAT
Component rates

In a bill of quantities, reinforcement and formwork are often measured and priced separately from the concrete. Use these component calculators when pricing RC elements individually.

💧
Drainage pipework
per m supply & lay
£25 – £350 / m
What is it

Drainage pipework covers the supply and laying of underground drainage pipes, typically uPVC for foul and surface water, or concrete for larger sizes and adoptable public sewers. The rate covers trench excavation, granular pipe bedding, pipe supply and jointing, and initial haunching — but not the full trench backfill, compaction or disposal of spoil. Pipe diameter and trench depth are the primary cost drivers.

Rate range
Cheap
£25 – £55 / m
Typical
£55 – £150 / m
High
£150 – £350 / m

Supply and lay (excl. full backfill and disposal) in GBP. Excludes prelims, overhead & profit.

3 key cost drivers
Pipe diameter
100mm uPVC is cheap and quick. 300mm concrete requires larger excavations, heavier plant and significantly more bedding. Larger pipes also cost more per metre to supply.
Depth of cover
Shallow drains (<1.5m) are quick to lay. Deep drains require shoring, slower working, more backfill and sometimes dewatering — all of which multiply the cost per metre.
Ground conditions
Easy-dig ground lets plant work quickly. Hard or waterlogged ground requires more excavation effort, dewatering and trench support — all adding to the per-metre rate.
Estimator

Supply and lay budgeting guide only — not a tender price.

£20 – £45 / m
Supply and lay · excl. full backfill, disposal, manholes, prelims, O&P
Exclusions
  • Manholes and inspection chambers (priced separately)
  • Full trench backfill and compaction
  • Disposal of excavated material
  • Trench support and shoring
  • Dewatering
  • Surface reinstatement (tarmac, flags, topsoil)
  • Testing and commissioning
  • Preliminaries, overhead and profit
  • VAT
Manholes
per nr supply & construct
£800 – £8,000 / nr
What is it

Manholes (inspection chambers) provide access to underground drainage systems for maintenance and inspection. Precast concrete ring manholes are the standard choice — fast to construct and cost-effective. Brick-built manholes are used for non-standard sizes or where precast cannot be craned in. The rate covers excavation, concrete base, chamber construction, benching, step irons, cover slab and access cover and frame. Depth is the single biggest cost driver.

Rate range
Cheap
£800 – £1,800 / nr
Typical
£1,800 – £4,000 / nr
High
£4,000 – £8,000+ / nr

Supply and construct per manhole in GBP. Excludes drainage pipework connections, prelims, overhead & profit.

3 key cost drivers
Depth
A shallow 1m precast manhole is simple. At 3m+ the structure requires more rings, deeper excavation with shoring, heavier plant for lifting and significantly more labour. Cost scales non-linearly with depth.
Construction type
Precast concrete ring manholes are fast and relatively cheap. Brick-built in-situ manholes are used for non-standard sizes or deep chambers. Labour cost is significantly higher for brick construction.
Access
An open site with crane access makes installation straightforward. Restricted access — in a live road, next to a building, or in a tight compound — dramatically increases cost and programme.
Estimator

Per manhole budgeting guide only — not a tender price.

£700 – £1,400 / nr
Supply and construct · excl. pipework connections, reinstatement, prelims, O&P
Exclusions
  • Drainage pipework connections (priced per metre separately)
  • Duct and cable entries
  • Specialist covers (non-standard loading, recessed, security)
  • Traffic management for road manholes
  • Road reinstatement
  • Preliminaries, overhead and profit
  • VAT
🛳
Asphalt surfacing
per m² supply & lay
£15 – £120 / m²
What is it

Asphalt surfacing covers the supply and laying of bituminous surfacing to roads, car parks, paths and paved areas. A full construction typically has two layers: a base course (binder or lower layer) and a wearing course (the finished surface). The rate covers material supply and laying only — it assumes the sub-base is already in place. Area size, number of layers and accessibility are the main drivers. Large open areas with paving machines are cheap; small patching in restricted locations is expensive.

Rate range
Cheap
£15 – £28 / m²
Typical
£28 – £65 / m²
High
£65 – £120 / m²

Supply and lay in GBP. Assumes sub-base already prepared. Excludes prelims, overhead & profit.

3 key cost drivers
Number of layers
A base course only is cheapest. A wearing course only is for overlays. Both layers together represent a full new construction — approximately double the single-layer rate.
Area
Large areas (500m²+) allow paving machines to work efficiently with minimal setup cost per m². Small areas require hand laying or small plant — expensive regardless of specification.
Access and constraints
Open road or car park with good access is straightforward. Restricted areas around plant, in tight car parks or near buildings require hand laying, smaller plant and slower progress.
Estimator

Supply and lay budgeting guide only — not a tender price.

£36 – £67 / m²
Supply and lay · assumes sub-base in place · excl. sub-base, kerbing, prelims, O&P
Exclusions
  • Sub-base excavation and construction
  • Kerbing and edging (priced separately)
  • Road markings and studs
  • Traffic management
  • Existing surface removal and disposal
  • Drainage channels and gullies
  • Preliminaries, overhead and profit
  • VAT
Kerbing
per m supply & bed
£30 – £180 / m
What is it

Kerbing is the supply and fixing of edge restraints to roads, paths and hardstandings. Precast concrete kerbs are the standard choice for roads and car parks — cost-effective, durable and quick to lay on straight runs. Granite kerbs are used in high-quality public realm and conservation areas. The rate covers supply of the kerb unit, concrete bed and backing. Layout geometry is a key productivity driver — straight runs are fast, but tight radius curves require individual cutting and setting, which is significantly slower.

Rate range
Cheap
£30 – £55 / m
Typical
£55 – £100 / m
High
£100 – £180 / m

Supply and bed in GBP. Excludes foundation excavation, sub-base, prelims, overhead & profit.

3 key cost drivers
Kerb type
Standard precast concrete kerbs (BS 7263) are cheap to supply. Granite kerbs are 3–5× more expensive per unit. Specialist units (dropped crossings, quadrant units) carry further premium.
Layout geometry
Long straight runs are fast — an experienced kerb layer can achieve 50m+ per day. Tight curves, radius kerbs and junctions require individual bedding and checking — productivity drops to 10–15m per day.
Foundation requirement
A simple concrete bed is the minimum. A full haunching on both sides — required for road kerbs taking traffic loading — uses significantly more concrete and labour per metre.
Estimator

Supply and bed budgeting guide only — not a tender price.

£27 – £52 / m
Supply and bed · excl. foundation excavation, sub-base, prelims, O&P
Exclusions
  • Foundation excavation and sub-base preparation
  • Road surfacing (asphalt or flags)
  • Drainage channels and gullies
  • Traffic management
  • Dropped crossings (priced separately — different unit)
  • Preliminaries, overhead and profit
  • VAT
Block paving / flags
per m² supply & lay
£40 – £220 / m²
What is it

Block paving and flags are hard surface materials used for roads, paths, driveways and public realm. Block paving uses small interlocking concrete units laid on a sand bed; flags (paving slabs) are larger units in concrete or natural stone. The rate covers supply and laying of the blocks or flags, sand bed and jointing — but assumes an existing prepared sub-base unless otherwise stated. Pattern complexity and material specification are the biggest variables.

Rate range
Cheap
£40 – £70 / m²
Typical
£70 – £130 / m²
High
£130 – £220 / m²

Supply and lay in GBP. Assumes prepared sub-base. Excludes prelims, overhead & profit.

3 key cost drivers
Material type
Standard concrete blocks are cheap and durable. Concrete flags are mid-range. Natural stone (sandstone, granite, yorkstone) carries a significant material premium — the stone often costs more than the laying.
Pattern complexity
Stretcher bond is fast. Herringbone, basketweave and mixed patterns require more cuts, careful setting out and slower laying. Each additional cut adds time and waste.
Sub-base requirement
If a good existing base is in place, the cost is for laying only. If excavation and a full Type 1 sub-base is required, this adds £30–60/m² to the total — a significant additional cost.
Estimator

Supply and lay budgeting guide only — not a tender price.

£22 – £40 / m²
Supply and lay · excl. sub-base, kerbing, edgings, prelims, O&P
Exclusions
  • Excavation and sub-base construction (if not selected above)
  • Kerbing and edging restraints (priced separately)
  • Drainage channels and gullies
  • Line marking or surface features
  • Specialist resin-bound or decorative surface treatments
  • Preliminaries, overhead and profit
  • VAT
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Buildings rates

Tap any activity to see the full breakdown

Tiling — floor
per m² supply & fix
£40 – £500 / m²
What is it

Tiling is the supply and fixing of ceramic, porcelain, or natural stone tiles to floors. The rate covers tile supply, adhesive, grout, and basic surface preparation. The tile itself is the single biggest variable — a £10/m² ceramic and a £300/m² marble are the same trade, same unit, completely different rate.

Rate range
Cheap
£40 – £80 / m²
Typical
£80 – £150 / m²
High
£150 – £500 / m²

All-in rates (tile supply + labour) in GBP. Excludes prelims, overhead & profit.

3 key cost drivers
Tile cost
The tile itself often costs more than the labour. £10/m² ceramic vs £300/m² marble = completely different job.
Cutting required
Small or irregular rooms mean more cuts, more waste, slower productivity. A big open floor is much faster to tile.
Tile size
Mosaics and small tiles take far longer to lay. Large format tiles cover ground quickly but need a flatter substrate.
Estimator

All-in budgeting guide only — not a tender price.

£115 – £165 / m²
All-in rate · tile supply + labour · excl. prelims, O&P
Exclusions
  • Preliminaries (site setup, supervision, welfare)
  • Contractor overhead and profit
  • Removal and disposal of existing tiles
  • Substrate preparation beyond minor patching
  • Waterproofing / tanking membranes
  • Movement joints and specialist trims
  • Underfloor heating supply or installation
  • Wall tiling (separate rate applies)
  • VAT
🧱
Blockwork
per m² supply & lay
£30 – £120 / m²
What is it

Blockwork is the construction of walls using precast concrete blocks bonded with mortar. It is the most common walling material in commercial and industrial construction — fast to lay, structurally capable, and easy to build around openings. Blocks range from 100mm lightweight partition blocks to 215mm dense aggregate blocks for structural or below-ground use. The rate covers blocks, mortar and laying — but not DPC, lintels, cavity fill, ties or any applied finish.

Rate range
Cheap
£30 – £48 / m²
Typical
£48 – £78 / m²
High
£78 – £120 / m²

Supply and lay in GBP. Excludes DPC, lintels, ties, finishes, prelims, overhead & profit.

3 key cost drivers
Block type and weight
100mm lightweight blocks are cheap to supply and quick to lay. 215mm dense aggregate blocks are heavier, slower to handle and more expensive. Dense blocks below ground carry an additional material premium.
Wall complexity
Simple straight walls with few openings are the fastest. Multiple openings, reveals, chases and complex returns reduce productivity significantly — more cuts, more setting out, slower overall output.
Working height
Ground floor walls under 3m are straightforward. Above 3m, scaffold lifts add cost and slow the operation. High gable walls require more scaffold moves and slower working at height.
Estimator

Supply and lay budgeting guide only — not a tender price.

£22 – £38 / m²
Supply and lay · excl. DPC, lintels, ties, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC)
  • Lintels over openings
  • Cavity wall ties and insulation
  • Movement joints and sealants
  • Plastering, rendering or any applied finish
  • Scaffold supply (usually in preliminaries)
  • Preliminaries, overhead and profit
  • VAT
🏠
Brickwork
per m² supply & lay
£55 – £250 / m²
What is it

Brickwork is the construction of walls using fired clay bricks bonded with mortar. Common bricks are used where the face is not visible; facing bricks are specified for external elevations and feature walls. The rate covers brick supply, mortar and laying to a standard bond. Decorative bonds, arches, soldier courses and complex detailing all reduce productivity significantly and should be noted separately when pricing.

Rate range
Cheap
£55 – £95 / m²
Typical
£95 – £165 / m²
High
£165 – £250 / m²

Supply and lay in GBP. Excludes DPC, lintels, scaffold, finishes, prelims, overhead & profit.

3 key cost drivers
Brick type and cost
Common bricks are cheap. Standard machine-made facing bricks are mid-range. Hand-made or specialist facing bricks are expensive — the material cost alone can represent 60% of the total rate.
Bond and complexity
Standard stretcher bond is the fastest. English or Flemish bond uses more bricks and more cuts per m². Feature panels, arches and string courses are significantly more time-consuming to set out and lay.
Quantity
Large areas of repeating brickwork allow continuous gang working. Small isolated panels — parapet cappings, feature insets, repairs — carry a high setup cost per m² regardless of the brick used.
Estimator

Supply and lay budgeting guide only — not a tender price.

£60 – £108 / m²
Supply and lay · excl. DPC, lintels, scaffold, finishes, prelims, O&P
Exclusions
  • Damp-proof courses (DPC)
  • Lintels and arch formers
  • Cavity wall ties and cavity insulation
  • Pointing and repointing (priced separately)
  • Scaffold supply (usually in preliminaries)
  • Rendering or other applied finish
  • Preliminaries, overhead and profit
  • VAT
🖌
Internal plastering
per m²
£8 – £45 / m²
What is it

Internal plastering is the application of plaster to internal walls and ceilings to create a smooth surface for decoration. A skim coat over plasterboard is the most common modern approach — thin, fast and relatively cheap. A full two-coat system on blockwork or masonry is more substantial. A three-coat system on old, uneven or specialist substrates is the most expensive. The rate covers materials and labour only — not boarding, rendering, painting or any other trade.

Rate range
Cheap
£8 – £15 / m²
Typical
£15 – £28 / m²
High
£28 – £45 / m²

Labour and materials in GBP. Excludes boarding, painting, prelims, overhead & profit.

3 key cost drivers
System type
A skim coat on new plasterboard is one thin coat applied quickly. A two-coat render and set on blockwork uses more material and time. A three-coat system on old masonry requires careful preparation of each coat — the most expensive option.
Surface complexity
Simple flat walls in large rooms are fast to plaster. Rooms with many reveals, window boards, arch details and curved surfaces require careful setting out and more time per m² regardless of the system.
Area
Large continuous areas allow plasterers to work efficiently. Small isolated areas — single walls, patching, making good — carry a high setup cost per m². Minimum call-out charges apply.
Estimator

Labour and materials budgeting guide only — not a tender price.

£9 – £18 / m²
Labour and materials · excl. boarding, painting, prelims, O&P
Exclusions
  • Plasterboard or substrate boarding (priced separately)
  • Beads, stops and mesh reinforcement at junctions
  • Painting and decorating
  • Specialist fire-rated or acoustic plasters
  • Making good after services installation
  • Preliminaries, overhead and profit
  • VAT
🏚
External rendering
per m²
£18 – £120 / m²
What is it

External rendering is the application of a mortar or polymer-based coat to external masonry walls for weather protection and a decorative finish. Traditional sand and cement render is the most basic and cheapest. Monocouche (one-coat polymer) render is now the commercial standard. Silicone or decorative renders are the premium end. Access via scaffold is a major cost in all scenarios and is usually priced separately in preliminaries.

Rate range
Cheap
£18 – £32 / m²
Typical
£32 – £68 / m²
High
£68 – £120 / m²

Labour and materials in GBP. Excludes scaffold, prelims, overhead & profit.

3 key cost drivers
Render specification
Sand cement is cheap but labour-intensive and prone to cracking. Monocouche is one coat — faster and more durable. Silicone and through-colour renders carry a material premium of 3–5× over traditional render.
Substrate condition
Flat, clean new blockwork renders quickly. Old masonry with varying suction or previous coatings may require hacking off, treatment and additional preparation coats before rendering can begin.
Access and height
Ground floor work on a simple elevation is straightforward. Multi-storey facades, complex profiles and tight sites all require more scaffold and slower working. Scaffold cost is usually priced separately in prelims.
Estimator

Labour and materials budgeting guide only — not a tender price.

£12 – £22 / m²
Labour and materials · excl. scaffold, prelims, O&P
Exclusions
  • Scaffold supply and erection (usually in preliminaries)
  • Hacking off existing render (priced separately)
  • Movement joint formation and sealants
  • Window and door reveals (often priced by the item)
  • Painting or other applied finish (separate rate)
  • Insulated render systems (EWI) — different product and rate
  • Preliminaries, overhead and profit
  • VAT
Tiling — wall
per m² supply & fix
£35 – £400 / m²
What is it

Wall tiling covers the supply and fixing of tiles to internal walls — kitchens, bathrooms, commercial wet rooms and feature walls. The mechanics are similar to floor tiling but productivity differs: cutting is more intensive around fixtures and fittings, adhesive application is vertical, and grout joints are often narrower. As with floor tiling, the tile specification is the single biggest material cost variable.

Rate range
Cheap
£35 – £70 / m²
Typical
£70 – £160 / m²
High
£160 – £400 / m²

All-in rates (tile supply + labour) in GBP. Excludes prelims, overhead & profit.

3 key cost drivers
Tile cost
The tile dominates the rate. A cheap ceramic at £8/m² and a premium Italian porcelain at £120/m² are the same labour activity — but produce completely different all-in rates.
Layout complexity
A simple splashback above a worktop is fast. Full-height tiling in a bathroom with multiple pipe penetrations, shower trays and horizontal borders requires extensive cutting and careful setting out.
Tile size
Small mosaic tiles are slow and labour-intensive. Standard 300×600 tiles are the most productive format for wall tiling. Large format tiles are heavier to handle and harder to cut around obstacles.
Estimator

All-in budgeting guide only — not a tender price.

£77 – £97 / m²
All-in rate · tile supply + labour · excl. prelims, O&P
Exclusions
  • Waterproofing / tanking membranes (wet rooms)
  • Substrate preparation (boarding, levelling)
  • Grout sealing and specialist treatments
  • Movement joints and trim profiles
  • Removal and disposal of existing tiles
  • Floor tiling (separate rate applies)
  • Preliminaries, overhead and profit
  • VAT
Sand cement screeding
per m²
£12 – £55 / m²
What is it

Sand cement screed is a levelling layer applied over a concrete floor slab to provide a flat, durable surface ready for floor finishes. Traditional sand and cement screed is mixed and laid by hand or pump. Liquid screed (anhydrite or calcium sulphate) is pump-applied and self-levelling. Screed is measured by area and priced per m² at a specified thickness. Large open areas are cheap; specialist screeds and small awkward areas are significantly more expensive.

Rate range
Cheap
£12 – £20 / m²
Typical
£20 – £35 / m²
High
£35 – £55 / m²

Labour and materials in GBP. Excludes underfloor heating pipework, floor finishes, prelims, overhead & profit.

3 key cost drivers
Screed type
Traditional sand cement is the cheapest but requires curing time and careful laying. Liquid anhydrite screed is pump-applied and self-levels — faster for large areas but more expensive per m². Self-levelling compound is the most precise and most expensive.
Thickness
A 40mm screed uses less material than a 75mm. Bonded screeds on good bases can be thinner. Unbonded screeds on insulation require greater thickness for structural integrity. More material equals more cost, directly.
Area
Large open floor plates allow efficient gang working and minimal waste. Small or compartmented areas — corridors, plant rooms — require significantly more labour per m² for the same specification.
Estimator

Labour and materials budgeting guide only — not a tender price.

£11 – £21 / m²
Labour and materials · excl. UFH, floor finishes, prelims, O&P
Exclusions
  • Underfloor heating pipework and manifolds
  • Insulation below screed
  • Edge insulation strips
  • Floor finishes (tiles, carpet, vinyl)
  • Concrete slab below (priced separately)
  • Specialist screeds (heavyweight, chemical resistant)
  • Preliminaries, overhead and profit
  • VAT
🖌
Painting & decorating
per m²
£4 – £35 / m²
What is it

Painting and decorating covers the application of paint to interior walls, ceilings, joinery and metalwork. The rate varies enormously depending on the surface preparation required — new plasterboard with a mist coat and two top coats is cheap and fast; old surfaces with multiple layers, staining and damage can require significant prep before painting begins. Premium paints, specialist coatings (fire-retardant, epoxy, anti-mould) and high working heights all add to the rate.

Rate range
Cheap
£4 – £8 / m²
Typical
£8 – £18 / m²
High
£18 – £35 / m²

Labour and materials in GBP. Excludes specialist coatings, scaffold, prelims, overhead & profit.

3 key cost drivers
Surface preparation
New plasterboard needs a mist coat and minimal prep. Old surfaces may need washing, sugar soaping, sanding, filling and priming before painting can begin. On large areas, prep can take as long as the painting itself.
Paint quality and coats
Trade emulsion at 2 coats is the baseline. Premium paints with 3 coats, specialist anti-mould, fire-retardant or epoxy coatings all carry higher material costs. Specialist coatings can be 5–10× the cost of standard emulsion.
Working height
Standard ceiling height (under 3m) is straightforward. Above 3m, painters need hop-ups or scaffold towers. High ceilings, atria and stairwells add significant cost — slower working, more equipment, higher risk.
Estimator

Labour and materials budgeting guide only — not a tender price.

£3 – £6 / m²
Labour and materials · excl. specialist coatings, scaffold, prelims, O&P
Exclusions
  • Wallpaper, fabric or specialist wall coverings
  • Joinery and metalwork painting (priced by item or run)
  • External painting (different system, separate rate)
  • Scaffold supply and erection
  • Removal and disposal of old coatings (e.g. lead paint)
  • Rendering or plastering preparation
  • Preliminaries, overhead and profit
  • VAT
Suspended ceilings
per m² supply & fix
£18 – £100 / m²
What is it

Suspended ceilings are false ceilings hung below the structural soffit using a grid system and ceiling tiles or panels. They allow services to run in the void above and provide acoustic and fire performance. Standard 600×600 exposed grid and tile systems are ubiquitous in commercial offices. Concealed grid systems give a cleaner look. Specialist tiles (acoustic, fire-rated, humidity-resistant) and bespoke layouts carry significant premiums.

Rate range
Cheap
£18 – £30 / m²
Typical
£30 – £58 / m²
High
£58 – £100 / m²

Supply and fix in GBP. Excludes lighting, services, scaffold, prelims, overhead & profit.

3 key cost drivers
Grid and tile specification
Standard 600×600 exposed grid with plain tiles is the cheapest. Concealed grid systems require more labour and cost more per m². Specialist acoustic, fire-rated or wet-area tiles carry significant material premiums.
Ceiling height
Low ceilings (under 3m) are quick to install with hop-ups. Higher installations require scaffold or MEWP, which slows the operation and adds equipment cost. The hanging rods and wires must also be longer.
Area and layout
Large, regular floor plates allow efficient grid layout with minimal cuts. Small rooms, many columns, circular layouts and complex ceiling levels all require significant additional cutting and setting out time.
Estimator

Supply and fix budgeting guide only — not a tender price.

£17 – £33 / m²
Supply and fix · excl. lighting, services, scaffold, prelims, O&P
Exclusions
  • Lighting fixtures (supply and installation)
  • Mechanical services grilles, diffusers and terminals
  • Sprinkler heads and fire detection devices
  • Acoustic treatment above the grid (mineral wool quilt)
  • Demountable partitions that meet the ceiling line
  • Scaffold or MEWP (usually in preliminaries)
  • Preliminaries, overhead and profit
  • VAT
📋
Drylining partitions
per m² supply & fix
£30 – £140 / m²
What is it

Drylining partitions are non-loadbearing internal walls built from a steel stud frame lined with plasterboard on both faces. They are fast to build, flexible and easy to adapt — the dominant method for internal subdivision in commercial buildings. Standard partitions use 70mm studs with a single layer of 12.5mm board each side. Fire-rated and acoustic partitions use additional layers of board and acoustic insulation. The rate covers stud, track, board, insulation (if specified) and fixings — not skimming, painting, or services.

Rate range
Cheap
£30 – £48 / m²
Typical
£48 – £82 / m²
High
£82 – £140 / m²

Supply and fix in GBP. Excludes skimming, painting, services, doors, prelims, overhead & profit.

3 key cost drivers
Partition type
Standard single-layer partitions are the most common and cheapest. Fire-rated partitions need double boarding and specialist products. Acoustic partitions add resilient bars, multiple board layers and acoustic quilt — all of which add material and labour.
Height
Partitions under 3m are quick to frame and board. Higher partitions need heavier stud sections, longer boards, more fixings, and may need top bracing. Very high partitions require working at height which adds cost.
Complexity
Simple long straight runs allow efficient board cutting with minimal waste. Multiple junctions, door openings, service penetrations and returns all break the run and require more cutting, more fixings and more time.
Estimator

Supply and fix budgeting guide only — not a tender price.

£22 – £38 / m²
Supply and fix · excl. skimming, painting, services, prelims, O&P
Exclusions
  • Skim coat plastering or taped and jointed finish
  • Painting and decorating
  • Electrical and mechanical services within partitions
  • Door sets and frames (priced separately)
  • Acoustic / fire stopping at junctions
  • Scaffold or MEWP for tall partitions
  • Preliminaries, overhead and profit
  • VAT
First Choice QS
First Choice QS
Build a high-paying QS career · community & tools

Reinforcement (rebar)

RC Concrete component

Per tonne supply & fix — often priced separately in a BoQ

Reinforcement (rebar)
per tonne supply & fix
£900 – £2,500 / t
What is it

Reinforcement is the supply and fixing of steel reinforcement bars (rebar) within concrete elements. In a bill of quantities, rebar is often measured and priced separately from the concrete and formwork. The rate per tonne covers bar supply, delivery, cutting and bending to schedule, and fixing in position including tying wire, spacers and supports. Bar diameter, quantity and fixing complexity are the primary cost drivers.

Rate range
Cheap
£900 – £1,200 / t
Typical
£1,200 – £1,800 / t
High
£1,800 – £2,500 / t

Supply and fix in GBP. Excludes concrete, formwork, prelims, overhead & profit.

3 key cost drivers
Bar size and type
Large straight bars (T25, T32) are fast to fix per tonne. Small bars (T10, T12) require more cuts, more ties and more handling time — the same weight takes much longer to place.
Fixing complexity
Simple mats or straight bars in an open slab fix quickly. Congested column cages with complex shapes, laps and links are slow and require skilled fixers throughout.
Quantity
Large tonnages reduce the amortised cost of mobilisation, delivery and setup. Small quantities on a minor job carry a premium — there is no economy of scale.
Estimator

Supply and fix budgeting guide only — not a tender price.

£1,150 – £1,750 / t
Supply and fix · excl. concrete, formwork, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Formwork supply and striking
  • Reinforcement mesh (A-type — priced separately)
  • Post-tensioning cables or tendons
  • Stainless steel or specialist alloy bars
  • Preliminaries, overhead and profit
  • VAT

Formwork

RC Concrete component

Per m² supply, fix & strike — often priced separately in a BoQ

📐
Formwork
per m² supply, fix & strike
£25 – £200 / m²
What is it

Formwork is the temporary mould into which concrete is poured. It must be erected before the pour, propped and checked, then struck (removed) after the concrete has cured. The rate covers supply of formwork materials, erection, striking and cleaning for reuse. Formwork is often the most expensive component of a reinforced concrete element — a complex bespoke form can cost more per m² than the concrete itself.

Rate range
Cheap
£25 – £55 / m²
Typical
£55 – £110 / m²
High
£110 – £200 / m²

Supply, erect and strike in GBP. Excludes concrete, rebar, prelims, overhead & profit.

3 key cost drivers
Element type
Flat slab formwork on a repetitive floor plate is the most efficient. Walls need two-sided forms. Complex shaped elements need bespoke carpentry — the most expensive category.
Repetition and reuse
Proprietary systems designed for multiple reuses amortise cost over many cycles. Bespoke one-off timber forms bear their full fabrication cost in a single use — dramatically higher per m².
Area and complexity
Large repetitive areas allow efficient gang working and minimal cuts. Small areas with multiple openings and projections require far more labour per m² regardless of the system.
Estimator

Supply, erect and strike budgeting guide only — not a tender price.

£65 – £115 / m²
Supply, erect and strike · excl. concrete, rebar, prelims, O&P
Exclusions
  • Concrete supply and placement
  • Reinforcement supply and fixing
  • Temporary propping beyond standard (priced separately)
  • Permanent lost formwork (e.g. Cordeck)
  • Specialist surface finishes to formed faces
  • Preliminaries, overhead and profit
  • VAT